Ten Mile Road, Cherry Lane to Ustick Road

General Description

This project is substantially complete as of 9/30/15. 

Ten Mile Road, Cherry Lane to Ustick Road

  • Widen Ten Mile Road from 2-lanes to 4/5-lanes
  • Add curb, gutter, sidewalk and bike lanes
  • Widen and install traffic signals at Ten Mile/Cherry Lane and Ten Mile/Ustick intersections
  • Construction for this project is planned for 2015 (formerly 2014)
  • Right-of-way acquisition for this project will occur in 2013 

Improvements at the Ustick and Ten Mile intersection were completed in September 2012. Click here to learn more about the intersection project.

Time Frame

Start Date: Construction 2015
End Date: TBD