Ustick Road, Linder Road to Locust Grove Road Projects

General Description

Project Update as of 2/16/17:  Temporary widening on the north side of the road will be finished in late February. Storm water, irrigation, and the City of Meridian pipe work, and utility work is on-going. Meridian Road, between Ustick and Fairview, will be CLOSED February 18-27 for pipe and utility work.

Ustick Road and Meridian Road Construction Video
Click to watch the Construction Video

Ustick Road, Linder Road to Locust Grove Road

  • Widen Ustick Road to five lanes with curb, gutter, detached sidewalks and bike lanes
  • Retain existing sidewalk where practical
  • Widen Ustick Road and Meridian Road intersection to include:
    • Dual left turn lanes
    • Right turn lanes
    • Additional thru lanes
  • Install a pedestrian signal on Ustick Road just west of 3rd Street and Settlers Park entrance
  • Evaluate Ustick Road and Venable Lane intersection for a two-way stop, a traffic signal or a roundabout

Project Purpose

  • Improve motorist, pedestrian, and bicyclist safety
  • Accommodate future traffic volumes

Materials from the August 8, 2013 Open House

Materials from the open house can be found on the right side of the screen under "Related Documents".

 

 

Time Frame

Start Date: Fall 2016
End Date: Fall 2017