Projects
Current Project
 
PROJECT MANAGER
 
Cody Homan
387-6109
choman@achdidaho.org
 
SUBSCRIBE
 
Subscribe for updates to this project to be sent to your email.
Your Name: 
Your Email:  
Locust Grove Road, Comisky Street to Commander Street

General Description

This project is substantially complete as of 10/08/15.

Locust Grove Road, Comisky Street to Commander Street
          
 

  • Install sidewalk on the east side of Locust Grove Road north of Strauss Road, and along the west side of Locust Grove Road south of Commander Street .

Schedule:

  • Design:  2015
  • Right of Way:  2015
  • Construction:  2015

Time Frame

Start Date: TBD
End Date: TBD