Plaza Drive Extension, 2nd St.to Iron Eagle Dr.

General Description

Project Update as of 2/28/17:  The Preconstruction Meeting will be held on March 28. The anticipated Notice to Proceed is May 1.

  • Construct new roadway alignment to include two travel lanes
  • Multi-use path on north side of Plaza Drive 
  • Bike lanes
  • Four-way stop controlled intersection at Plaza Drive and 2nd Street
  • Pedestrian improvements and striping to existing Plaza Drive
  • Storm water improvements
  • The City of Eagle will provide landscaping between the road and the multi-use path.

Materials from the January 22, 2015 Open House

  Project Purpose
  • Improve connectivity, traffic circulation, economic vitality and quality of life in downtown Eagle.

Time Frame

Start Date: May 2017
End Date: End of August 2017