Project Update as of 2/28/17:  The Preconstruction Meeting will be held on March 23. The Notice to Proceed is April 5.

Construction to start in April

As early as April 5, 2017 construction will begin on the 1st Street, Broadway Avenue to Pine Avenue project. Construction is anticipated to be complete by the end of June. The project includes:

Traffic and Construction Impacts
During construction there may be the following impacts: general construction noise, dust, equipment back up alarms and ground vibration. Work is expected to occur between 7 a.m. and 7 p.m.

Project Description

  • Constructing curb, gutter and sidewalk on both sides of W. 1st Street between Broadway and Pine.
  • Installing a new sewer line.
  • Reconstructing the roadway.
  • Check out the Project Exhibit under "Related Documents" to look at the planned improvements.
Project Purpose
  • Improve pedestrian connectivity and safety for children walking to Meridian Elementary School

Time Frame

Start Date: Summer 2017