Construction Update as of 8/25/20: The epoxy overlay is complete. Remaining work includes permanent striping.
General Description:
This summer, the Ada County Highway District will begin work on the 2020 Bridge Preventative Maintenance project. This project consists of minor repairs of the existing Main Street bridge and installation of an epoxy overlay of the bridge deck. Work will be done on the Main Street Bridge between Garden Street and Whitewater Park Boulevard.
Construction update as of 7/17/20: The epoxy overlay is complete. Bridge joints were replaced the week of June 29th. Remaining work includes permanent striping.
Kadee Porter
projects@achdidaho.org