Ada County Highway District

Linder Road and Deer Flat Road Intersection Project

Stay Informed! Sign up to receive our emailed construction updates.

Construction Update as of 12/11/2020: Asphalt paving has been postponed until the Spring of 2021 due to cold temperatures and the presence of frost in the ground. Crews placed temporary striping on Thursday, December 10th, to help delineate travel lanes until the spring.  We apologize for any inconvenience caused by this delay. 

The asphalt paving originally scheduled for the week of November 23rd was delayed due to weather. The paving is tentatively rescheduled for the week of December 7th; however, this will depend on the temperature being warm enough to properly place asphalt. If the ground is still frozen, even with warmer daytime temperatures, that would undermine the quality of the asphalt.

Please note, during asphalt paving there will be temporary delays (up to 20 minutes) as paving operations cross side streets, driveway approaches, and work through the intersection. There will be flaggers to assist motorists. 

If temperatures do not allow for asphalt paving then that work would be postponed until warmer weather in the Spring of 2021. Traffic will remain in its current configuration until that time. 

Asphalt paving scheduled for the week of November 23rd was delayed due to weather. Paving operations will resume when the temperature allows. More information will be provided before paving resumes. 

As early as Monday, November 23rd, crews will begin asphalt paving at the Linder and Deer Flat intersection. This work is expected to complete before Thanksgiving. There may be temporary travel delays, up to 20 minutes, as crews pave through the intersection. Motorists are encouraged to plan extra time into their commute and to drive with caution. There will be flaggers to assist as needed. Please note, asphalt paving is weather dependent and the schedule is subject to change.

Permanent striping will begin late November or early December, weather permitting. Traffic will be shifted into the final configuration in mid-December.

The west half of the north leg of Linder was paved on October 30th and traffic was shifted on November 3rd. Crews have begun excavating and placing base gravels on the east half of the north leg of Linder. On the west leg of Deer Flat the paving on the south half is complete. Crews are working on finishing base gravels on the north half. There is ongoing work on concrete curb, gutter, and sidewalk on all four legs of the intersection.

Crews are working on the north leg of Linder and the west leg of Deer Flat. Utility relocations were completed September 16th

Construction is anticipated to be complete in Winter 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

 

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

Construction Update as of 07/17/2020: Construction to start on Monday, May 18th. Tree removals started on May 21st. Utility relocations started in advance of construction and are on-going. Asphalt has been milled on the west side of Linder Road and the south side of Deer Flat Road. Crews are working on underground storm drainpipe and seepage bed installation. They are also working on installation of the new traffic signal.

Traffic Info: Traffic was shifted to the east side of Linder Road and the north side of Deer Flat Road. Motorists should expect some delay when traveling through the construction zone. 

Construction is anticipated to be complete in October 2020.

Utility work began in January and will continue throughout the project. When complete the intersection will feature:

  • Right turn lanes.
  • Single left turn lanes, with accommodations made for future dual left turn lanes on Linder Rd.
  • Partially controlled access on the west leg of Deer Flat Rd. with an extruded curb, as it exists today, for safety.
  • Curb, gutter, and sidewalk. Sidewalk will extend to match existing sidewalk on the east leg of Linder Rd. and the south leg of Deer Flat Rd.
  • Right turn lane into Reed Elementary and Kuna High.

Learn More:

Linder and Deer Flat Intersection Design

Construction Impacts

Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

*Timeline subject to change due to COVID-19.

.....

Utility Work

Idaho Power will begin utility relocations in advance of construction. Idaho Power is expected to begin work mid-January and the work will last several weeks. Expected impacts during utility relocations may include some daytime flagging and lane restrictions.

General Description:

September 10, 2018 ROW Acquisition

The project is in the right of way acquisition phase and should be complete by late fall/early winter.  This project utilizes federal funding and construction is planned to begin in FY 2020.  

11/17/16 Community Open House 

Materials from the open house can be found under "Related Documents" to the right of your screen.

.....

Project Description

The Ada County Highway District (ACHD) is designing improvements for the Linder Road and Deer Flat Road intersection. The purpose of the project is to improve safety, increase capacity and improve pedestrian connectivity. It will feature:

  • Right turn lanes.
  • Dual left turn lanes on southbound Linder Road.
  • Controlled access on the north leg of Linder Road and the west leg of Deer Flat Road with an extruded curb.
  • Curb, gutter, and sidewalk. Sidewalks extend to match existing sidewalks on the east leg of Linder Road and the south leg of Deer Flat Road.
  • Right turn lane into Reed Elementary and Kuna High.

 

February 25, 2015  Commission Decision

The ACHD Commission choose to move forward with Alternative 1 - Signalized Intersection.

 

November 6, 2014 Linder and Deer Flat Intersection Open House

Learn about the alternatives for the Linder and Deer Flat Intersection by reviewing the materials under "Related Documents" to the right.

......

The Ada County Highway District (ACHD) is starting preliminary work on a concept design for the Linder Road and Deer Flat Road intersection area, a neighborhood that features a sports park, several schools, and a variety of businesses.

The goal of the concept is to engage the community and determine what type of intersection will efficiently and safely meet the future needs of all users - motorists, pedestrians and bicyclists. We are in the very initial stages, which means that we don't have a design, nor have we chosen an alternative at this time. Please review the newsletter to learn more.

 

Project Description

  • Develop and evaluate intersection alternatives.
  • The purpose of the redesign will be to improve safety, increase capacity and improve pedestrian connectivity
  • This is a Federal aid project.

 

Time Frame

Start Date: FY 2020
End Date: TBD

We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster