Ada County Highway District

Bogus Basin Road, Curling Drive to 550' north of Curling Drive

Construction Update as of 9/16/19:  Utility work has begun and is ongoing. Crews have moved to the east side of the roadway in preparation for the associated work. Block walls were delivered 9/3/19, and construction on the block walls started on 9/4/19. Wall construction should be complete the week of 9/23/19. Paving will be done after the remaining work is completed as to be able to pave the full width at once.

Construction Update as of 9/06/19:

Utility work has begun and will continue while the roadway improvements are progressing. Crews have moved to the east side of the roadway in preparation for the associated work. Block wall materials were delivered 9/03/19. Block wall construction started 9/04/19. Paving will be done after the remaining work is completed as to be able to pave the full width at once.

General Description:

ACHD will be constructing curb, gutter and attached sidewalk on both sides of Bogus Basin Road to fill in the sidewalk gap just north of Curling Drive. The project will also include adding a retaining wall near the mailboxes. The work is expected to be complete at the beginning of October 2019.

Construction impacts could include lane restrictions with flaggers, general construction noise, dust, equipment backup alarms, and ground vibration.

Please note that the contractor will coordinate with property owners to maintain access during construction. Please be especially cautious when getting your mail as crews will be working near the mailboxes,.

Crews typically work weekdays, 7 a.m. to 7 p.m.

Time Frame

 

Start Date:
June 2019
End Date:
October 2019

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster