Project Update as of 11/16/17:  This project is substantially complete as of November 15. 

General Description: 

  • Construct curb, gutter and sidewalk on the southeast side of Cameron Street between Hummel Drive and the Aurora Drive/Randolph Drive intersection.
  • Reduce on-street parking to one side in certain areas.
  • Replace curb and gutter on northwest side of Cameron.
  • Resurface whole roadway.

 

Project Purpose

  • Provide a safe route for children walking to school
  • Increase pedestrian connectivity within the neighborhood

 

March 16, 2015 Open House Materials

 Learn about the Fairfield sidewalk project that will be constructed at the same time.

Time Frame

Start Date:
Beginning of May 2017
End Date:
August 2017