Ada County Highway District

Columbus Street, Overland Road to Kootenai Street

Construction Update as of 9/25/19: Asphalt paving is complete on Columbus Street. Minor work remains, including small sections of concrete sidewalk and landscape repair.

Construction Update as of 9/16/19:  Kootenai is substantially complete. Columbus is closed between Overland and Kootenai through the second week in September. Concrete work on the east side of Columbus is mostly complete. Crews are placing concrete for curb, gutter, sidewalk, and driveways on the west side of Columbus. Asphalt paving started Friday, September 6th and was completed Tuesday, September 10th. Minor work remains, including manhole adjustments, striping, and landscape repair. Underground work on Overland is complete. Crews are prepping for curb and gutter.

Construction Update as of 9/06/19:

Columbus is closed between Overland and Kootenai through the first week of September. Concrete work on the east side of Columbus is mostly complete. Crews are placing concrete for curb, gutter, sidewalk and driveways on the west side of Columbus. Asphalt paving is tentatively scheduled for Friday, September 6th, but is dependent on pipe repairs and concrete work being complete. Kootenai is substantially complete. Underground work on Overland is complete. Crews are prepping for curb and gutter.

Update as of 8/26/19:

Columbus is closed between Overland and Kootenai. Crews working on placement of base gravels and prepping for curb, gutter, and sidewalk. Concrete work is started the week of August 19th and is ongoing.

Utility relocations are ongoing.

There was a preconstruction conference on February 8th.

Originally, this project was to be constructed during the spring/summer of 2018. Unfortunately, the bids we received for construction were not satisfactory. As a result, the project went back out to bid the fall of 2018 and construction is set to begin late February 2019.

......

General Description:

  • Construct curb, gutter and sidewalk on both sides of Columbus Street.
  • Maintain on-street parking on both sides of the street.
  • Rebuild the roadway.
  • Sharrows (shared lane markings) will be painted on the street after the rebuild.
  • View the project design under "Related Documents" to the right of your screen.

Project Purpose

  • Increase pedestrian connectivity.

  

Design:
2015-2016
Right-of-Way:
Fall 2016
Construction:
2019

Time Frame

Start Date:
February 2019
End Date:
Mid Summer 2019

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster