Construction Update as of 6/14/19:

Crews are working on the storm drain system on Overland Road. Work on the railroad tracks is complete and Overland re-opened on April 17th.

Suez is working on a water line replacement on Overland and Columbus. This work will last through the end of May.

This project is being built in conjunction with improvements on Columbus Street, Overland to Kootenai and Kootenai, Vista to Federal Way. There is ongoing utility relocations for both Kootenai and Columbus. Columbus between Overland and Kootenai is currently closed for irrigation pipe installation and storm drain pipe installation.

There was a preconstruction conference held on February 8th. Crews will begin work as early as the week of February 18th.

Update

Originally, this project was to be constructed during the spring/summer of 2018. Unfortunately, the bids we received for construction were not satisfactory. As a result, the project will go back out to bid the fall of 2018 and we anticipate construction will begin spring 2019.

.....

Project Description:

  • Construct curb, gutter and sidewalk on both sides of Overland Road between Columbus Street and Federal Way to match existing.
  • Prepare roadway for future bike lanes.
    • This project will help make room for future bike lanes that will be added when the street is resurfaced in the future.

 

Project Purpose:

  • Increase pedestrian connectivity and safety.
  • Prepare roadway for future bike lanes.

 

Design:
N/A
Right-of-Way:
Fall 2016 - Summer 2017
Construction:
2018

Time Frame

Start Date:
Late February 2019
End Date:  Mid Summer 2019

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster