Ada County Highway District

Valley Street, Lake Hazel Road to La Grange Street

Construction Update as of July 2, 2020: A preconstruction conference was held on May 21st.  Utility relocations will start on June 15th, the contractor will begin their work after the utility relocations are complete.Storm drain installation scheduled to start the week of July 6th.

General Description:
Install approximately 860 linear feet of new curb, gutter, sidewalk, and remove and replace select portions of sidewalk on the west side of Valley Street in front of the school. Upgrade and install curb ramps, driveway approaches, crosswalks, and luminaires as needed. Upgrade a seepage bed.

Design:
FY2019
Right-of-Way:
FY2019
Construction:
2020

Time Frame

Start Date:
June 2020
End Date:
Late Summer 2020

Return to Projects

Related Documents

Project Manager

Chris Dayley
 projects@achdidaho.org


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster