Ada County Highway District

2020 Green Stormwater Implementation

Construction Update as of October 13th, 2020: The notice to proceed is May 29th.

Alley at 4th/5th: Utilities are complete.

Alley at 9th/10th: This alley has been postponed until Spring 2021.

General Description:

New stormwater collection systems will be implemented in two downtown Boise alleys.

  • The alley that runs along Idaho Street and Bannock Street between 4th Street and 5th Street.
  • The alley that runs along 9th Street and 10th Street between Miller Street and Myrtle Street.

 

Design:
FY2018
Right-of-Way:
FY2018-19
Construction:
2020

Time Frame

Start Date: Late Spring 2020
End Date:
Fall 2020