2019 Downtown Boise Maintenance

Construction Update as of 10/18/19:  

Idaho Street, 4th to 8th Street: Mill and pave is complete. Striping will start the week of October 13th, temperatures permitting. Manholes will be raised October 9th-10th.

Idaho Street, 13th Street to 16th Street:  Milling and paving is currently scheduled for November 4-7, weather dependent.

Main Street, 4th to 8th Street: Mill and pave is complete. Striping will start the week of October 13th, temperatures permitting. Manholes will be raised October 9th-10th.

Main Street, 1st to 4th Street: Mill and pave will now be the week of October 21st, weather permitting. This work was postponed a week due to weather.  Concrete placement at 1st/Main Street will be placed the week of October 7th.

15th Street: Ongoing concrete work. New concrete between Main Street and Idaho Street scheduled for the week of October 21. Electrical work from Front Street to Bannock Street. Milling and paving is currently scheduled for November 10-15, weather dependent and pending the completion of CCDC's work.

For up-to-date information on this and other work, please see the ACHD Roadwork in the Area map

There was a preconstruction conference held on May 7th.

General Description:
The Ada County Highway District will begin its 2019 Downtown Boise Maintenance which is pavement rehabilitation project. Construction is scheduled to start early May 2019 and run through late September 2019. Work includes repaving, replacing some curb, gutter sidewalk and pedestrian ramps and utility relocation and replacements. Project segments include:

2019 Downtown Boise Implementation - HB312

  • 16th Street, Front Street to State Street: COMPLETE
  • 15th Street, Front Street to State Street: Ongoing electrical and concrete work.  Milling and paving is currently schedule for November 10-14, pending weather and the completion of CCDC's work.
  • Bannock Street, 16th Street to 15th Street: COMPLETE
  • Bannock Street, Capitol Boulevard to 2nd Street: COMPLETE

Main Street and Idaho Street, 16th Street to Broadway Avenue - HB312

  • Main Street, 16th Street to 13th Street: Minor work remains
  • Main Street, 10th Street to 8th Street: Minor work remains
  • Main Street, 8th Street to 4th Street:  Milling and paving complete, permanent striping the week of October 13th
  • Main Street, Capitol Boulevard to Broadway Avenue: Milling and paving expected the week of October 13th
  • Idaho Street, 16th Street to Broadway Avenue: Milling and paving from 13th to 16th streets is currently scheduled for November 4-7, weather dependent.

Time Frame

Start Date:
May 2019
End Date:
Fall 2019

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster