Construction Update as of April 15, 2021: On Saturday, April 17th, there will be a traffic swap moving the project into Phase 2. Crews will begin milling the northbound lane on Monday, April 19th. Phase 2 is expected to take approximately 3 weeks, weather permitting.
Past Construction Updates:
Southbound lane is being excavated. Jersey barrier is in place for safety.
There was a preconstruction meeting on March 11th. Notice to proceed is March 25th. Work on Phase 1 has begun.
This project will have 4 phases and 4 segments. Two phases on the northern half and two on the southern half. Half the road will be built at a time for each phase. Phase 1 and 2 are on the south portion of the road where the traffic will be controlled by a signal. Phases 3 and 4 will be on the northern half with flaggers.
Here is a map of all the projects in the Gowen Road/Pleasant Valley area this year.
General Description:
This spring the Ada County Highway District will begin work on the 2021 Arterial and Collector Capital Maintenance project. This is a pavement rehabilitation project. Crews will be reconstructing Pleasant Valley Road from Amyx Lane to Hollilynn Drive as part of ACHD's Pavement Management Program.