Construction update as of 8/10/18:  Paving is ongoing and is nearly complete. Work has begun on the new Forest Service Trailhead. Crews are also installing new inlets and concrete curb. Work is being done with flaggers; drivers should expect 15-minute delays.

General Description:

Work consists of maintenance improvements such as a pavement overlay; new and replacement barrier and guardrail installations; new and replacement concrete curb installations; minor reconstruction of curve locations; pipe replacements; signage improvements; installation of snow pole markers; and paving, widening, and improving turnout locations. Work also includes construction of a new trailhead, parking facility, and other amenities for the Boise National Forrest.

This work will occur from Milepost 9 (the Ada County/Boise County line) to Milepost 16.2 (the Bogus Basin Recreation Area).

Time Frame
Start Date: Early June, 2018
End Date:  Late August, 2018

Return to Projects

Related Documents

Project Manager

Brian McCarthy
projects@achdidaho.org


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster