Ada County Highway District

Cloverdale Road, Fairview Avenue to Ustick Road

Construction Update as of 8/17/18:   Asphalt paving is complete. Concrete sidewalk work is nearly complete. The High-Intensity Activated crosswalk (HAWK) beacon was activated on August 7th. The roadway is expected to open to five lanes in mid August but there will continue to be minor work throughout the month of August, including fence replacement and landscape repair.

General Description:

  • Widen roadway to five lanes with curb, gutter and sidewalk, using existing sidewalk where feasible
  • Add bike lanes
  • Install two pedestrian signals on Cloverdale Road at Granger Street and S. Clover Meadows Drive
  • Build a retaining wall on east side of roadway, between Stillwater Drive and Bowmont Street

Project also includes

  • A drainage pond near the south property line of the Cloverdale Nursery
  • Work at Fairview Avenue and Cloverdale Road intersection to smooth out rough surface

October 24, 2013 Open House

Click on the image to enlarge:

Aerial.gif

 

 

Design:
FY2015
Right-of-Way:
FY2016
Construction:
2018

Time Frame

Start Date:
January 2018
End Date:
September 2018