Ada County Highway District

Linder Road, Ustick Road to McMillan Road

Sign up to receive emailed construction updates!

This project is considered substantially complete.

Construction Update as of 9/25/19:  Linder Road between Ustick and McMillan is substantially complete. Asphalt paving on Linder Road between McMillan and Chinden is complete. Minor work remains, including concrete sidewalk and landscape repair.

Construction Update as of 9/06/19:

Linder Road between Ustick and McMillan is substantially complete. Minor work remains, including landscape repair and fencing. Stormdrain pipe installation between McMillan and Chinden is complete. Concrete curb and gutter has been placed. Asphalt paving is scheduled for the week of September 9th.

Construction Update as of 8/26/19:

Linder Road between Ustick and McMillan re-opened the morning of August 16th. Minor work remains including landscape repair and fencing.

Asphalt paving started on August 6th and will take 4 to 5 days to complete. Striping, sign installation, and remaining concrete work will be done the week of August 12th. The road will re-open to one lane in each direction on August 16th.

Excavation is complete. Crews are working on placement of base gravels and underground electrical work. Asphalt paving is scheduled for the week of August 5th. Linder Road between Ustick and McMillan remains closed.

Starting June 20th to August 16th, Linder Road between Ustick Road and McMillan Road will be closed. The road closure is intended to allow crews to finish the roadway improvements on Linder Road between Ustick and McMillan before the next school year begins.

Alternative Routes During the Closure:

  • School access to Sawtooth Middle School will be from Stone Valley Drive.
  • Linder Road between Ustick and Monument Drive will have a hard closure. Residents on the west side of Linder can enter/exit from Ustick Road via Towerbridge Way or from Ten Mile Road.  
  • Linder Road between Monument Drive and McMillan Road will be local traffic only. Residents on the east side can enter/exit Linder Road from Loretta Street. Residents on the west side can enter/exit Linder Road from Coppercloud Way. 
  • Through traffic headed north/south can use Ten Mile Road or Meridian Road.

There is ongoing utility work. Traffic was swapped onto the temporary paving on the east side of Linder on March 31st.

Construction Update as of 5/17/19:

Crews are working on storm drain installation and roadway improvements on the west side of Linder Road between Ustick and McMillan.

There will be a road closure at Stone Valley Drive on Thursday, May 9th to Monday, May 13th. This is an extension of the closure which was originally expected to end on Friday, May 9th. This closure will be for work on storm water pipe installation and utility relocations. The crosswalk at Stone Valley will be open with flaggers to help students cross the road if needed. There will be lane restrictions on Linder Road during the day.

Crews are working on pedestrian ramp improvements, excavation, and storm drain installation. There is ongoing utility work. Traffic was swapped onto the temporary paving on the east side of Linder on March 31st.

Separate from ACHD's project, there will be a closure on Linder Road, Cayuse Creek to Chinden for sewer work being done by a developer. The closure will be from March 25th to April 7th.

Crews are working on the east side of Linder between Ustick and McMillan to prepare for temporary paving. There is ongoing work on curb, gutter and sidewalk.

Construction began the week of February 18th. This initial phase of work includes utility relocations and work on irrigation crossings. There is ongoing work on curb, gutter and sidewalk.

About the Project:

At the end of February construction will begin on the Linder Road, Ustick to Chinden projects. When complete Linder Road will feature:

Construction Impacts
Impacts could include lane restrictions with flaggers, temporary closures, general construction noise, dust, equipment back up alarms, and ground vibration.

Other Upcoming Construction Projects

Over the next several years this area will have several local and state roadway/intersection projects under construction by ACHD, as well as the Idaho Transportation Department (ITD). Check out this construction map to view upcoming projects and anticipated construction years.
.....

August 31, 2017 Open House

All the displays and handouts from the August 31 open house are under "Related Documents" to the right of your screen.

General Description:

  • Widen Linder Road between Ustick Road and McMillan Road to two lanes in each direction, with a center turn lane
  • Add bike lanes
  • Install curb, gutter and sidewalk
  • Install a signalized pedestrian crossing at Monument Street

Project Purpose

  • Increase safety for those that walk, bike and drive
  • Improve traffic flow

Linder Road, Cayuse Creek Drive to Chinden Boulevard

Learn about future plans to widen the short segment of Linder Road between Cayuse Creek Drive and Chinden Boulevard.

 


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere