Construction Update: May 20, 2022: Southbound lane closed. Placing base aggregate for roadway. Placing string line for curb. Sidewalk placement ongoing.
Construction Update: May 6, 2022: Southbound lane closed. Placing base for roadway. Placing string line for curb installed. Sidewalk placements will begin after curb is placed.
Construction Update: April 29, 2022: Southbound lane closed. Placing base for roadway. Placing string line for curb on the west side. Sidewalk placements will begin after curb is placed.
Construction Update: April 8, 2022: Installing storm drain. Intermountain Gas work ongoing. Southbound lane closed. Placing base for road. Placing string line for curb. Sidewalk after curb.
Construction Update: April 1, 2022: Installing Storm Drain. Intermountain Gas work ongoing. Southbound lane closed. Placing base for road.
Construction Update: March 25, 2022: Installing storm drain. Intermountain Gas work ongoing. Excavating for subgrade. Seepage beds being installed. Southbound lane closed.
Construction Update: March 4, 2022: Installing Storm Drain. Intermountain Gas work ongoing. Excavating for Subgrade. Southbound lane closed.
Construction Update: February 25, 2022: Installing Storm Drain. Intermountain Gas work ongoing. Excavating for Subgrade. Southbound lane closed.
Construction Update: February 18, 2022: Preconstruction meeting held November 15th. Notice to proceed is January 30th, 2022. Irrigation work ongoing. Southbound lane closed.
Construction update: February 10, 2022: Preconstruction meeting held November 15th, Notice to proceed is January 30th, 2022. Utility work ongoing in advance of construction. Irrigation work started, structures arriving January 28. Southbound lane closed.
Construction update: January 13, 2022: Utility work ongoing in advance of construction.
Construction update: December 13, 2021: ACHD will begin construction on Christine Street from Northview Street to Ustick Road. Construction is scheduled to start in January 2022 and substantial completion is planned for mid-summer 2022. Utility companies have already started to relocate existing overhead and underground facilities.
General Description:
Project Purpose:
Timeline:
Reid Selmer
projects@achdidaho.org