Construction Update as of October 1, 2021: Demo complete. Grade work complete. East and west side curbing complete. DIs have been placed. Sidewalk work ongoing. Nearly complete. Main line paving complete. Concrete driveway work ongoing. Miscellaneous landscape repair work ongoing.
Construction Update as of September 23, 2021: Demo complete. Grade work complete. East and west side curbing complete. DIs have been placed. Sidewalk work ongoing - nearly complete. Main line paving half complete.
Construction Update as of September 17, 2021: Demo complete. Grade work ongoing. East and west side curbing nearly complete. Minor radius work remaining. 2 out of the 3 DIs have been placed. Sidewalk work ongoing. Paving is scheduled for September 21st.
Construction Update as of September 10, 2021: Demo complete. Grade work ongoing. East and west side curbing nearly complete. Minor radius work remaining. Sidewalks are expected to be complete next week. Paving is scheduled for September 14th.
Construction Update as of September 3, 2021: Miscellaneous demo continues. Grading work ongoing. East side curbing nearly complete. West side to start early next week. Utility work ongoing. Formwork for sidewalks has been partially set.
Construction Update as of August 26, 2021: Miscellaneous demo continues. Grading work ongoing. Curbing is expected to start next week. Utility work ongoing. Light poles have been set and relocated to clear sidewalk.
Construction Update as of August 19, 2021: Miscellaneous demo work continues. Grading work is ongoing. Curbing is expected to start next week. Utility work is ongoing. Light poles have been set and relocated to clear sidewalk.
Construction Update as of August 13, 2021: Contractor has mobilized to the site. Miscellaneous demo work has started. Contractor has trimmed trees. Survey stakes have been set for construction limits, etc. Milling complete
Construction Update as of August 6, 2021: The contractor has mobilized to the site. Miscellaneous demo work has started. Survey stakes have been set for construction limits.
Construction Update as of July 30, 2021: ACHD is coordinating street light replacement and relocation with the City of Boise and Idaho Power. The contractor anticipates starting work on August 2nd.
Construction Update as of July 6, 2021: ACHD is coordinating street light replacement and relocation with the City of Boise and Idaho Power.
Construction Update as of June 11, 2021: The Preconstruction Meeting was held on May 21st. ACHD is currently waiting on project submittals from the contractor before a Notice to Proceed is issued.
Construction Update as of April 29, 2021: The Ada County Highway District will start construction on the 38th Street project between Bush Avenue and Sunset Avenue as early as mid-May. Construction is anticipated to be complete in the fall.