**This project is substantially complete**

Construction Update, August 19, 2022 - Concrete work is complete. Paving and striping is scheduled for August 18-19. Pedestrian signals will be activated on August 23rd. 

Construction Update, August 12, 2022 - Concrete work on Boise Street is complete. Contractor working on create and signal improvements. 

Construction Update, July 29, 2022 - Concrete work on Boise Street is complete. Signal work is on-going. Ten Mile is closed south of Boise Street. Contractor working on concrete and signal improvements. 

Construction Update, July 22, 2022 - Concrete work on Boise Street is complete. Signal work is on-going. Ten Mile is closed south of Boise Street. Contractor working on concrete and signal improvements and utility work for the City of Kuna. 

Construction Update, July 15, 2022 - Contractor started work on Boise Street on June 13th. Installing conduit and pole bases for pedestrian signals. Concrete placements are ongoing. 

Construction Update, July 8, 2022 - Preconstruction meeting was held May 23rd. Contractor started work on Boise Street on June 13th. Installing conduit and pole bases for pedestrian signals. Concrete removal ongoing. 

In early June, the Ada County Highway District (ACHD) will start construction on the Kuna Middle School Zone Project. The purpose of this project is to improve safety near Kuna Middle School. Construction is anticipated to be completed late in the summer of 2022.

Project Description:

  • Install a Pedestrian Hybrid Beacon (PHB) at the intersection of Ten Mile Road and Boise Street at the northern cross walk. A Rectangular Rapid Flashing Beacon (RRFB) is also being installed across Boise Street, halfway between Ten Mile Road and Strike Way.
  • Place additional street lighting on the southeast corner of the Ten Mile Road and Sego Prairie Street intersection.
  • As part of this project, a water line across Ten Mile Road at the south leg of the Boise Street and Ten Mile Road intersection will be installed.
  • School zone beacons will be installed on Ten Mile Road and Boise Street near Kuna Middle School.

Construction Impacts:

  • The Ten Mile Road and Boise Street intersection will be temporarily closed during construction
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms, and ground vibration    
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved  
  • The contractor will work with homeowners to minimize impacts 

 

Return to Projects

Related Documents

Project Manager


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster
Privacy Policy