2021 Residential Capital Maintenance

Construction Update: September 30, 2022

  • E. Washington Avenue, E. 4th Street to N. Cathy Ave - Road is closed. Grade work ongoing. Concrete work is expected to be complete next week. 
  • 4th St. - Washington to Janie - Landscapers on site intermittently. Substantially complete. 
  • E. 2nd Street, E. Idaho Ave to E. Carlton Ave - Work from Pine to Carlton ongoing. 
  • E.5th Ave, E. Franklin Road to E. Bower Street - Minor concrete items remain, driveway approaches remain - waiting on landscaping.  
  • E. Bower Street, N. Main Street to east end - Minor concrete items remain. Waiting on landscaping.
  • E. 5th Street, State Ave to the north end - Work substantially complete

Construction Update: September 23, 2022

  • E. Washington Avenue, E. 4th Street to N. Cathy Ave - Road is closed. Grade work ongoing.
  • 4th St. - Washington to Janie - Landscapers on site intermittently. Utility pole relocations complete and existing poles removed. Minor concrete work remains. 
  • E. 2nd Street, E. Idaho Ave to E. Carlton Ave - Milling has occurred. Pipe work ongoing. Concrete work and landscaping work remaining.  
  • E.5th Ave, E. Franklin Road to E. Bower Street - Minor concrete items remain, driveway approaches remain - waiting on landscaping.  
  • E. Bower Street, N. Main Street to east end - Minor concrete items remain, driveway approaches remain - waiting on landscaping.  
  • E. 5th Street, State Ave to the north end - Minor concrete work remaining

Construction Update: September 16, 2022

  • E. Washington Avenue, E. 4th Street to N. Cathy Ave - Road is closed. Milling started September 9th. 
  • 4th St. - Washington to Janie - Landscapers on site. Still waiting on utility pole relocations.
  • E. 2nd Street, E. Idaho Ave to E. Carlton Ave - Road is closed. Milling started September 9th. 
  • 5th Ave - Landscapers on site. Still waiting on utility pole relocations. 
  • E.5th Ave, E. Franklin Road to E. Bower Street - Mainline asphalt paving is complete. 
  • E. Bower Street, N. Main Street to east end - Mainline asphalt paving is complete.  

Construction Update: September 9, 2022

  • E. Washington Avenue, E. 4th Street to N. Cathy Ave - Road is closed. Milling started September 9th. 
  • 4th St. - Washington to Janie - Landscapers on site. Still waiting on utility pole relocations.
  • E. 2nd Street, E. Idaho Ave to E. Carlton Ave - Road is closed. Milling started September 9th. 
  • 5th Ave - Landscapers on site. Still waiting on utility pole relocations. 
  • E.5th Ave, E. Franklin Road to E. Bower Street - Lane taper for new ped ramps on Franklin/5th complete. The contractor will pull TTC off the roadway each night. Mainline asphalt paving is complete. 
  • E. Bower Street, N. Main Street to east end - Mainline asphalt paving is complete.  

Construction Update: September 2, 2022

  • 4th St. - Washington to Janie - Landscapers on site. Still waiting on utility pole relocations.
  • 5th Ave - Landscapers on site. Still waiting on utility pole relocations. 
  • E.5th Ave, E. Franklin Road to E. Bower Street - Concrete demo complete. Vaults and pipe work continues. Lane taper for new pedestrian ramps on Franklin/5th complete. The contractor will pull TTC off the roadway each night. Anticipated pave date is September 6th and 7th. 
  • E. Bower Street, N. Main Street to east end - Concrete demo complete. Grade prep and formwork has started. Pipe work continues. Shutdown completed August 25th to lower the City of Meridians water line to clear the conflict with a new drainage line. Anticipated pave date is September 6th and 7th. 

Construction Update: August 26, 2022

  • 4th St. - Washington to Janie - Landscapers on site. 
  • 5th Ave - Landscapers on site. 
  • E.5th Ave, E. Franklin Road to E. Bower Street -Concrete demo complete. Vaults and pipe work continues. Lane taper for new ped rams on Franklin/5th started. The contractor will pull TTC off the roadway each night. 
  • E. Bower Street, N. Main Street to east end - Concrete demo nearly complete. Grade prep and form work has started. Pipe word continues. Shutdown scheduled for August 25th to lower the City of Meridian's water line to clear the conflict with a new drainage line.

Construction Update: August 19, 2022

  • 4th St. - Washington to Janie - Concrete placements nearly complete. Waiting on power poles to relocate before final placements. Working with other utilities to relocate and remove existing services. Paved week of July 25th. 
  • 5th Ave - Utility coordination continues. Concrete placements nearly complete. Paved week of July 25th. Waiting on power poles to relocate before final placements. 
  • E.5th Ave, E. Franklin Road to E. Bower Street -Concrete demo nearly complete. Vaults and pipe work continues. Lane taper for new ped ramps on Franklin/5th started. Contractor will pull TTC off the roadway each night. 
  • E. Bower Street, N. Main Street to east end - Concrete demo nearly complete. Grade prep and form work has started. Pipe work continues. Existing water line conflicts with irrigation. Contractor is working with the City to get the water main lowered. 

Construction Update: August 12, 2022

  • 4th St. - Washington to Janie - Concrete placements nearly complete. Waiting on power poles to relocate before final placements. Working with other utilities to relocate and remove existing services. Paved week of July 25th. 
  • 5th Ave - Utility coordination continues. Concrete placements nearly complete. Paved week of July 25th. Waiting on power poles to relocate before final placements. 
  • E.5th Ave, E. Franklin Road to E. Bower Street -Concrete demo started. Pipe work started. 
  • E. Bower Street, N. Main Street to east end - Concrete demo started. Pipe work started. Existing water line conflict with irrigation. 

Construction Update: August 5, 2022 

  • 4th St. - Washington to Janie - Concrete placements nearly complete. Working with other utilities to relocate and remove existing services. Paved July 25th.  
  • 5th Ave - Utility coordination continues. Concrete placements nearly complete. Paved week of July 25th.
  • E.5th Ave, E. Franklin Road to E. Bower Street - Milling complete. Concrete demo started. Pipe work started. 
  • E. Bower Street, N. Main Street to east end - Milling complete. Concrete demo started. Pipe work started.

Construction Update: July 22, 2022 

  • 4th St. - Washington to Janie. Concrete placements continue. Utility work complete for the City of Meridian. Working with other utilities to relocate and remove existing services. Anticipated pave date set for July 25th. 
  • 5th Ave - Utility coordinator continues. Concrete placements continue. Anticipated pave date set for July 25th.
  • E.5th Ave, E. Franklin Road to E. Bower Street - next phase. Valves and Manholes have been adjusted to grade. Milled July 21st.
  • E. Bower Street, N. Main Street to east end - Valves and Manholes have been adjusted to grade. Milled July 20th. 

Construction Update: July 15, 2022 - 4th St. - Washington to Janie. Concrete placements continue. Utility work complete for City of Meridian. Working with other utilities to relocate and remove existing services. Anticipated pave date set for July 20/21. 5th Ave. - Fire hydrants have been relocated and flushed. City of Meridian has been overseeing this process. Utility coordination continues. Concrete placement continues. Anticipated pave date set for July 20/21.

Construction Update: July 8, 2022 - 4th St. - Washington to Janie. Contractor working on misc. demo. Concrete placements anticipated to start this week. Utility work complete for City of Meridian. Working with other utilities to relocate and remove existing services. 5th Ave - Contractor working on misc. demo. Fire hydrants have been relocated and flushed. City of Meridian has been overseeing. Utility coordination continues. 

Construction Update: July 1, 2022 - 4th St. - Washington to Janie. Contractor working on misc. demo. Hope to start placing concrete next week. Utility work complete for City of Meridian.  5th Avenue - Contractor working on misc demo. FH have been relocated and flushed. City of Meridian has been overseeing. Utility coordination continues. No issues to report from Dairy Days. 

Construction Update: June 24, 2022 - 4th St. - Washington to Janie. Contractor milled Friday June 17th. Utility work complete. 5th Avenue - Contractor milled Friday, June 17th. ACHD has coordinated with the contractor to ensure access during Dairy Days scheduled for June 25th. 

Construction Update: 4th St. - Washington to Janie. Pipe work on going. Concrete demo and prep underway. Contractor anticipates milling on Friday, June 17th. 5th Ave. Contractor may start milling Friday, June 17th. 

General description:
The Ada County Highway District will start construction on the 2021 Residential Capital Maintenance Project in early May. This pavement maintenance project primarily consists of removing and replacing all or a portion of the existing asphalt pavement (depending on the street segment). Work also includes reconstructing adjacent curb ramps to meet modern standards and minor stormwater pipe replacements in downtown Meridian. Construction is anticipated to be complete fall of 2022.

Streets to be reconstructed:

  • 2nd Street, Idaho Avenue to Carlton Avenue
  • 4th Street, Broadway Avenue to State Avenue
  • 4th Street, Washington Avenue to North End
  • 5th Avenue, State Avenue to North End
  • 5th Avenue, Franklin Road to Bower Street
  • Bower Street, 2nd Street to East End
  • State Avenue, 2nd Street to Cathy Lane
  • Washington Avenue, 4th Street to Cathy Lane

Construction impacts:

  • Temporary on-street parking impacts 
  • Lane restrictions 
  • Temporary closures 
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with property owners to minimize impacts
  • General construction noise, dust, equipment backup alarms, and ground vibration

Time frame:

Start Date: May 2022

End Date: Fall 2022