24th Street Road and Bridge Projects

January 21, 2022 Update: Preconstruction meeting held November 12th. Notice to proceed was November 30th.  Suez is installing new waterline on Irene Street. Contractor installing culvert pieces starting at Irene.

January 13, 2022 Update: Preconstruction meeting held November 12th. Notice to proceed is November 30th. Suez installing new waterline on Irene Street.

December 9, 2021 Update: Preconstruction meeting scheduled for November 12th. Notice to proceed is November 30th. Anticipated start December 9th - Suez work.

November 4, 2021 Update: As part of the Ada County Highway District's (ACHD) Bridge Maintenance Program, ACHD will start construction on the 24th Street Bridge and Road Project between Irene Street and Bella Street early December. Construction is anticipated to be complete spring of 2022. The purpose of this project is to replace aging bridge structures, rehabilitate the street, and improve pedestrian connectivity. 

Construction Impacts:

  • Lane restrictions
  • Temporary on-street parking impacts
  • General construction noise, dust, equipment backup alarms and ground vibration
  • Crews will work from 7a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to maintain access

---

Project Description:

  • Replace three underground bridge structures over the Boise City Canal. The underground structures cross Bella and Irene near 24thand also run underneath 24th street between Bella and Irene.
  • Due to the extensive nature of the work, a full roadway rebuild will be necessary on 24th Street between Irene Street and Bella Street. This will also include adding sidewalks on both sides of the street.

 

Return to Projects

Related Documents

Project Manager

Chris Dayley