Construction Update: May 12, 2022: Working between Rose Hill and Alpine. Excavation complete prepping for curb and sidewalk. Cleaning road for opening purposes. Curb, gutter, and ped ramps. Concrete sidewalks and approaches being installed.
Construction Update: May 6, 2022: Irrigation work is ongoing. Working between Rose Hill and Alpine. Excavation complete prepping for curb and sidewalk. Cleaning road for opening purposes. Curb, Gutter, and ped ramps. Concrete sidewalks and approaches being installed.
Construction Update: April 15, 2022: Irrigation work is ongoing. Closure between Alpine and Bethel ongoing. Installing Sewer utilities anticipated finished April 18th. Working between Rose Hill and Alpine. Curb, Gutter, and ped ramps. Concrete sidewalks and approaches being installed. Suez will be installing water line starting March 14th Multiple road closures as work progresses.
Construction Update: April 8, 2022: Irrigation work ongoing. Closure between Alpine and Bethel ongoing. Installing sewer utilities. Working between Rose Hill and Alpine. Curb, Gutter, and ped ramps. Seepage bed being installed. Concrete sidewalks and approaches being installed. Suez will be installing water line starting March 14th. Multiple road closures as work progresses.
Construction Update: March 11, 2022: Irrigation work ongoing. Closure between Alpine and Bethel anticipated March 14th. Installing Sewer utilities. Working between Rose Hill and Alpine. Curb, Gutter, and ped ramps. Suez will be installing water line starting March 14th. Multiple road closures as they progress.
Construction Update: March 4, 2022: Irrigation work ongoing. Closure between Alpine and Bethel postponed - Waiting for equipment before closure can happen. Installing Sewer utilities. Working between Rose Hill and Alpine -Curb, Gutter, and pedestrian ramps. Suez will be installing water line starting March 7th. Multiple Road closures as they progress.
Construction Update: February 25, 2022: Irrigation work ongoing. Closure between Alpine and Bethel postponed. Waiting for equipment before closure can happen. Installing Sewer utilities. Working between Rose Hill and Alpine - Curb, Gutter, and ped ramps.
Construction Update: February 18, 2022: Preconstruction meeting held December 16th. Irrigation work ongoing. Closure between Alpine and Bethel anticipated Feb 21st.
Construction Update: February 3, 2022: Preconstruction meeting held December 16th. NTP scheduled for January 10th. Tree trimming and removal anticipated January 18th. Irrigation work anticipated starting January 24th. Road closed for irrigation between Bethel and Morris Hill Rd.
General Description
The original Roosevelt Street, Rose Hill to Emerald Street project started design in 2015 and since then ACHD has modified the design to incorporate improved bicycle and pedestrian facilities. Please see below for an updated description of the project as well as updated exhibits.
Roosevelt, Rose Hill to Alpine
Roosevelt, Alpine to Emerald
Existing on-street parking will be maintained on the west side of Roosevelt.
Updated Design Exhibits
Project Purpose