NW 8th Street, Pine Avenue to Cherry Lane

Construction Update: June 24, 2022 - Preconstruction meeting will be held on April 18th .  Notice to Proceed (NTP) is June 4th . Work will be done during the summer to minimize impacts to the school. 

Construction Update: March 25, 2022- As part of Phase 3 of the 2021 Federal Aid Capital Maintenance project, ACHD will begin work on NW 8th Street from Pine Avenue to Cherry Lane. Construction will begin in early June. Work will be done during the summer to minimize impacts to the school. 

 


 

Construction to Start Early June!

This summer, the Ada County Highway District will begin construction on NW 8th Street, from Pine Avenue to Cherry Lane. This project consists primarily of pavement rehabilitation and upgrades to bike lanes and adjacent pedestrian ramps. As part of this work, ACHD will also be upgrading existing stormwater infrastructure. Construction is anticipated to be completed early in the fall of 2022.

La construccion comenzara a principios de junio!

Este verano, el Distrito de Carreteras del Condado de Ada (ACHD) comenzara las obras de construccion sobre la NW 8th Street, entre Pine Avenue y Cherry Lane. El proyecto consiste principalmente en la restauracion de la pavimentacion y mejoras a los carriles para bicicletas y las rampas peatonales adyacentes. ACHD mejorara tambien la infraestructura de drenaje pluvial existente como parte de este trabajo. Se espera que el proyecto se finalice para principios de otono de 2022.

Construction Impacts 

  • Temporary closures
  • Temporary on-street parking impacts
  • Lane restrictions with flaggers
  • General construction noise, dust, equipment backup alarms, and ground vibration
  • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
  • The contractor will work with homeowners to minimize impacts

Impactos de la construccion

  • Cierres temporales
  • Cambios temporales en el estacionamiento en la calle
  • Restricciones de carriles con bandereros
  • Ruido general de construccion, polvo, alarmas de reversa de camiones y vibracion del suelo
  • Los equipos trabajaran de las 7 a.m. a las 7 p.m., salvo aprobacion distinta
  • El contratista trabajara con los vecinos para minimizar los impactos

Return to Projects

Related Documents

Project Manager

Stihles Clark
projects@achdidaho.org


We Drive Quality Transportation For All Ada County ~
Anytime...Anywhere

Ada County Highway District © 2017
For Questions or problems with this Web site contact the Webmaster
Privacy Policy