Construction Update October 15, 2021: Microseal work is complete. Parking stripes remaining.
Construction Update August 19, 2021: Microseal work is complete. Remaining work includes installation of pavement markings.
Construction Update August 6, 2021: Construction is moving along. Please note, these are the streets remaining:
Construction Update July 26, 2021: ACHD will begin maintenance on the segments listed below on July 26th, 27th, and 28th. Most of the work will be done at night. View the schedule here.
General Description:
Beginning in late July 2021, the Ada County Highway District (ACHD) will begin work on several Boise roads. This annual pavement maintenance project involves cleaning the surface of the existing asphalt, then applying a fast-drying asphalt-based sealant. This project is for preventative maintenance of the roadways. There will be closures in place for each segment of road with detour routes.
The following road segments are included in the program:
Brian McCarthy
projects@achdidaho.org