Full IFYWP Document 2020-2024

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Adoption Draft for Review

Table of Contents


Introduction

The 2020-2024 Integrated Five-Year Work Program (IFYWP) sets forth the strategies, projects and priorities which the Ada County Highway District (ACHD) will pursue over the next five years. The first two years of the Plan align with ACHD’s 2020 Budget, adopted on August 21, 2019. The remaining years set the focus for ACHD’s efforts for future budget years. The document allows elected officials, staff, partner agencies, and the public to work in a coordinated fashion to implement projects.

The Integrated Five-Year Work Plan works in support of various ACHD and partner agency foundational planning documents and is the implementing arm for these plans. The figure below illustrates how the IFYWP fits into the region’s overall planning framework.

A chart showing the planning framework for the Integrated Five-Year Work Plan


ACHD Vision, Mission, and Priorities and Strategic Plan

ACHD established its vision, mission, and priorities in 2011, with the intent of ensuring that all ACHD activities are focused on the best interest of the citizens we serve. The bottom line is that every choice ACHD makes must help to effectively and efficiently accomplish ACHD’s Vision, Mission and Priorities.

In June 2016, the ACHD Commission adopted a Strategic Plan to further refine and clarify the intent of its vision, mission, and priorities. The Plan included a resource allocation methodology that informs and guides development of the IFYWP. That methodology emphasizes maintenance and safety as ACHD’s primary focus. In addition, the Strategic Plan and Capital Improvements Plan (CIP) highlight the need to enhance the transportation system in response to the growth planned by ACHD’s land-use partners. Through the Strategic Plan, the Commission identified system enhancements to address congestion as ACHD’s secondary focus. The IFYWP was developed with these focus areas in mind.

ACHD Vision: Leading transportation innovation - Investing in communities

ACHD Mission: We drive quality transportation for all Ada County - Anytime, Anywhere!

ACHD Priorities, which will serve as the criteria for judging every choice we make going forward:

  1. Our People - Our competitive edge in the work place is the source of our strength. As such we will:
    • Maximize training
    • Invest in our people
    • Reward innovation, commitment to the mission and excellence across the board
  2. Effective and efficient execution, assuring:
    • Excellence in service and performance
    • Teamwork
    • Fiscal responsibility in expending taxpayer dollars
    • Responsiveness to regional and community needs
    • Customer service
    • The promotion of economic development with each community
    • The preservation of our multi-billion dollar infrastructure investment
    • Preparation for future growth
  3. Leaders in technology, design, and innovation
  4. Safety throughout the district for its employees and citizens

Plan Outline

The 2020-2024 IFYWP continues ACHD’s commitment to an “integrated” approach to planning and programming while maintaining fiscal responsibility in all its programming decisions. In 2018, the Commission recognized a need for additional funding in order to meet the investment levels required to fully implement ACHD plans over the next 20 years. As a result, the Commission placed an initiative to raise the Vehicle Registration Fee in Ada County on the November 2018 ballot. This initiative was not approved by the voters of Ada County and additional funding is not available.

In recognition of ACHD’s funding obligations, the Commission approved a revised Capital Allocation Methodology in May 2019. This methodology places as its top priority meeting the financial obligations of the District. Once these have been met, the Commission continues to keep its primary focus on providing for the safety and maintenance of the transportation system, followed by system enhancements as a secondary focus. A summary of these priorities is found below.

  1. Meet ACHD's Programming Obligations
    • Ensure compliance with applicable federal laws (Americans with Disabilities Act & Environmental Regulations)
    • 2008 Vehicle Registration Fee ballot commitments - Safe routes to school & congestion relief
    • Match Impact Fee collections with required general funds
  2. Primary Focus - Safety & Maintenance
    • Signals, Crossings, and Safety Projects with documented needs
    • Asset Management - Capital Maintenance & Bridges (Minor & Major if reserves available)
  3. Secondary Focus - System Enhancements
    • Neighborhood Plan & Bike Master Plan projects not funded by VRF
    • Non-Impact Fee Eligible Capital Improvement Plan Projects

The IFYWP is organized around ACHD’s commitment to these priorities. The introductory section of the IFYWP provides a status report on our efforts to implement the Strategic Plan, including the revised allocation methodology. In this way, the IFYWP serves as a tool to demonstrate accountability to the public to do what ACHD has said it will do. The remaining portion of the Plan identifies the projects to be completed over the next 5-7 years.


A Balanced Transportation System

In determining the scope of each project listed within the IFYWP, ACHD seeks to implement its Complete Streets Policy and meet the needs of all users within the project limits in order to take the most advantage of work going on in an area. ACHD has updated its Americans with Disability Act Transition Plan, its Bike Master Plan and continues to develop neighborhood bike and pedestrian plans to identify and reinforce the need for projects to be implemented in a comprehensive fashion, realizing benefits for all users through all types of projects.

This IFYWP demonstrates the impact of this action. Below is an example from one project within the IFYWP and its complete streets implementation approach. By looking at projects with this wholistic approach, ACHD can effectively invest in the communities and lives of the public it serves.

Different parts of a Capital project


Implementing the Strategic Plan

Meeting ACHD's Programming Obligations

Americans with Disability Act Transition Plan Implementation

In 2019, ACHD adopted an update to its Americans with Disabilities Act (ADA) Transition Plan. The ACHD ADA Self-Evaluation and Transition Plan provides a framework for the continuous improvement of Ada County Highway District's programs and facilities for people with disabilities. The Plan is intended to be a living document that is regularly updated as programs and services change, as barriers are removed, and new facilities come under ownership or control of ACHD. The Plan outlines a strategy for ACHD to progress toward compliance with the ADA, enacted on July 26, 1990, identifying physical barriers for persons with disabilities and a schedule to remove those barriers over time. The following is a summary of the pedestrian ramps and sidewalks identified as being non-compliant as part of the Update and those programmed to be brought into compliance in the FY2020-2024 IFYWP. In future years, the IFYWP will also show the number of locations brought into compliance.

Progress towards Implementation

A chart showing that ACHD has 322 of 1273 High Priority Ramps, 106 of 696 Medium Priority Ramps, and 399 of 7608 Low Priority Ramps programmed in the IFYWP.

2008 Vehicle Registration Fee Ballot Commitments - Safe Routes to Schools

ACHD’s efforts to provide safe routes to schools are focused on ensuring appropriate facilities exist to allow for children and adolescents to access their educational opportunities using active transportation modes. In 2008, the citizens of Ada County approved an increase in vehicle registration fees with the commitment that half of that increase would be dedicated toward providing safe routes to schools. ACHD is committed to fulfilling its commitment. Since that time, ACHD has completed 123 projects and has an additional 46 identified in the IFYWP.

Safe Routes to School Projects
Completed since 2008

  • 74 Pedestrian Projects (26 Additional Programmed)
  • 11 School Zone Enhancements (3 Additional Programmed)
  • 47 Crossing Improvements (26 Additional Programmed)
  • 3 Bikeway Projects Programmed

Match Impact Fee Collections with Required General Funds

The collection of impact fees on new development is ACHD’s primary funding source for addressing the impact of the region’s growth on the transportation system. These funds are only available to be spent on items deemed impact fee eligible through State Code and ACHD’s Impact Fee Ordinance. The impact fee eligible items as per these guiding documents include road and intersection widening, right-of-way acquisition, and storm drain facilities.

Many items deemed part of creating a complete street network are deemed not eligible for the use of impact fees. These include sidewalks and pedestrian crossings, reconstruction of existing vehicle lanes, bike facilities, and landscaping. These items must be funded using ACHD’s other sources of funding outside of impact fees. Ensuring adequate funding to cover these items is an essential part of ACHD’s mandate to ensure proper use of all available impact fee collections. In recognition of this, the IFYWP includes programming of all projected impact fee collections with the required match from other funding sources.

A diagram showing that ACHD projects to collect $102,440,000 in Impact Fees between 2020 and 2024.

ACHD’s Primary Focus Areas – Addressing Maintenance and Safety Needs

Pavement - On Target

  • Performance Goal: Maintain ACHD's network pavement condition in the "very good" category. Very good represents a 70-100 pavement condition index (PCI) score.
  • Current Condition
    • Arterials - Very Good (82 PCI)
    • Collectors - Very Good (82 PCI)
    • Locals - Very Good (82 PCI)

Bridges - On Target

  • Performance Goal: Maintain 99%+ of ACHD's bridges with a sufficiency rating of "Good/Better."
  • Current Condition
    • Bridges over 20' - 99.5% (220 out of 221)
    • Bridges 5' to 20' - 99.3% (564 out of 568)

Traffic Signals and Safety - On Target

  • Performance Goal: Maintain traffic signal in service rate at 99% or better. Address safety issues as they arise.
  • Current Condition
    • 99.99% In-Service Rate
  • IFYWP Safety and Accessibility Projects
    • 1 traffic calming project
    • 4 accessible pedestrian signal projects
    • 1 intersection improvement
    • 2 railroad crossing projects

ACHD’s Secondary Focus Area – System Enhancements

Neighborhood Pedestrian and Bicycle Plans

Since 2012, ACHD has adopted 10 neighborhood pedestrian and bicycle plans. These plans, an outgrowth of ACHD’s ADA Transition Plan and Bicycle Master Plan, identify active transportation projects important to the neighbors who live there. While there is no time horizon on when the projects identified in these plans will be built, ACHD seeks to make constant and continual progress towards completion. As of the end of FY2019, 258 out of 809 projects identified in these plans will be built or under construction.

Additional neighborhoods are being planned each year. As plans are completed, projects from those neighborhoods will be added below. Current additional plans to be completed include:

  • Eagle Neighborhood Plan (Underway)
  • Whitewater Park + VMP Boise Neighborhood Plan (Underway) – This is a subset of the North Boise Neighborhood Plan and projects will be incorporated into that Plan after adoption.
  • Garden City Neighborhood Plan (2020)
  • North Meridian Neighborhood Plan (2020)
  • South Meridian Neighborhood Plan (2021)
  • Kuna Neighborhood Plan (2021)

Progress towards Implementing Neighborhood Plans

A chart showing the projects already built, programmed in the IFYWP, or awaiting programming for each of the Neighborhood Bike and Pedestrian Plans completed

Bike Master Plan

In 2018, ACHD adopted an addendum to its 2009 Roadways to Bikeways Bike Master Plan. This addendum incorporated new facility types that have come into use since 2009 and established a matrix to determine the level of bicycle facility to use based on traffic volumes and posted speed limits. Additionally, this plan identified a network of low-stress bikeways to be implemented through the IFYWP that would provide an alternative to the arterial bike facility network. The addendum also updated the planned facilities map (arterial and low-stress) to reflect the information provided using the new matrix. Buildout out of this network is being audited at this time. A summary of the buildout of the network will be shown in future updates to the IFYWP.

Congestion Management

ACHD recognizes it cannot build its way out of congestion. System enhancements in the form of roadway widening are intended to “buildout” a robust system and provide added capacity where deemed feasible. A roadway is deemed “built-out” once the number of lanes built matches the planned lanes in ACHD’s Master Street Map. Once a roadway is “built-out”, congestion may still increase as land uses further develop. In these circumstances, ACHD will seek to make other operational type improvements to maximize efficiency of the built network. These types of projects are found within the Traffic Program in the IFYWP.

ACHD employs a level of service (LOS) measure for streets and intersections to assist in measuring expected driver comfort and identifying needed system enhancements. Roads and intersections are graded on a scale of A through F based on generalized thresholds of roadway utilization during the busiest hour of the day (peak hour). Per ACHD’s adopted policies, roadways classified as arterials are deemed to no longer have an acceptable level of services when rated as an F.

The chart below gives a status of roadway segments and intersections currently deemed LOS F and how they correspond to projects planned within this IFYWP. As you will note, some road segments and intersections are currently LOS F, but they are not identified in the IFYWP. These projects are not programmed due to lack of available funding and/or the roadway has reached its desired buildout for the land use context.

Construction Status of LOS F Intersections and Road Segments

A chart showing the roadway segments and intersections that are operating at a level of service F. This is broken down for years 2018 and 2019 and the current build out status of these locations. For details, please contact ACHD.

2016 Capital Improvement Plan

ACHD’s Capital Improvement Plan (CIP) uses model forecasts to project needed roadway system enhancements from new development over the next 20 years. The CIP is updated every 4 years, with the last update being adopted in 2016. One of the primary purposes for the CIP is to allocate the cost of growth to new development in the form of impact fees. Impact fees do not pay the full cost of roadway expansion as certain features, such as sidewalks and bike lanes, are not eligible for impact fees. Therefore, general fund revenue must also be available to match the impact fee revenue for projects to be completed.

The 2016 CIP identified the projects for which impact fees and general fund revenue could reasonably be expected. On average, ACHD would need to expend $37.6 million per year over the next 20 years on road and intersection enhancements in order to fully implement the 2016 CIP. The chart below shows programmed expenditures over the life of this IFYWP against that target. Based on currently expected revenue, ACHD would be $51 million short over the life of the IFYWP in fully funding CIP identified projects.

Funding in the IFYWP towards Implementing the CIP

A chart showing the annual spending on implementing the Capital Improvement Plan compared to an annual goal of $27.6 million.

Priority Corridors

In an effort to implement the CIP in a logical manner, the ACHD Commission has adopted a series of priority corridors. In programming and implementing these projects, ACHD takes a systematic approach representing two steps:

  1. Improve intersections first to take full advantage of corridor capacity prior to mainline widening.
  2. Widen corridors sequentially (from one end to the other) when traffic conditions warrant the widening.

The following shows identified priority corridors and their current status of completion.

  • Cloverdale R, Overland R / Chinden Blvd*
    • 4 Intersections - All Complete
    • 5 Roadway Segments - All Complete
  • Cloverdale R, Lake Hazel Rd / Overland Rd
    • 4 Intersections - 1 Complete, 2 Programmed, 1 Unfunded
    • 3 Roadway Segments - 1 Programmed, 2 Unfunded
  • Eagle Rd, Lake Hazel Rd / Victory Rd
    • 2 Intersections - 2 Programmed
    • 2 Roadway Segments - 2 Programmed
  • Fairview Ave, Linder Rd / Orchard St
    • 8 Intersections - 7 Complete, 1 Programmed
    • 9 Roadway Segments - On Hold per Commission Direction
  • Franklin Rd, Black Cat Rd / Cole Rd*
    • 10 Intersections - All Complete
    • 9 Roadway Segments - All Complete
  • Lake Hazel Rd, Eagle Rd / Orchard St Extension
    • 5 Intersections - 1 Complete, 4 Programmed
    • 5 Roadway Segments - 1 Complete, 4 Programmed
  • Linder Rd, Ustick Rd / Floating Feather Rd
    • 5 Intersections - 4 Complete, 1 Programmed
    • 6 Roadway Segments - 2 Complete, 2 Programmed, 2 Unfunded
  • Locust Grove Rd, Victory Rd / Ustick Rd
    • 5 Intersections - 3 Complete, 2 Programmed
    • 4 Roadway Segments - 2 Complete, 1 Programmed, 1 Unfunded
  • Maple Grove Rd, Lake Hazel Rd / Overland Rd
    • 3 Intersections - 3 Programmed
    • 3 Roadway Segments - 2 Programmed, 1 Unfunded
  • Orchard St, Lake Hazel Rd Extension / I-84
    • 1 Intersections - 1 Programmed
    • 2 Roadway Segments - 1 Complete, 1 Programmed
  • State St, Glenwood St / 27th St
    • 4 Intersections - 2 Complete, 2 Programmed
    • 4 Roadway Segments - 4 Programmed
  • Ten Mile Rd, Overland Rd / Chinden Blvd
    • 5 Intersections - All Complete
    • 5 Roadway Segments - 1 Programmed, 1 Unfunded
  • Ten Mile Rd, Deer Flat Rd / Overland Rd
    • 6 Intersections - 6 Programmed
    • 6 Roadway Segments - 1 Programmed, 5 Unfunded

External Funding Plan

The funding plan portion of the IFYWP focuses external funding efforts on the Commission’s approved focus areas adopted in the ACHD Strategic Plan (2016). External funding comes from funding sources that are not codified by State of Idaho code or fee regiment for use by the Ada County Highway District, with most of these funds coming from Federal Highway Administration programs. The funding plan ensures funding application efforts are timely and supported by the Commission. All local match funding will be reviewed and approved by Commission when the project agreement is presented for approval.

Federal Capital Maintenance

ACHD currently receives Surface Transportation Block Grant Program Transportation Management Area (STP-TMA) funding for qualified, capital maintenance work on Federal-aid Highway System Arterial and Collector roadways. Per Communities in Motion 2040, COMPASS programs 82% of STP-TMA funding for ACHD’s road maintenance needs, including but not limited to overlays, reclaims, rebuilds and micro seals. When available, STP-Urban funds may be used for capital maintenance projects within Kuna or Star. The federal match requirement for STP funding is 7.34% of project cost. Federal maintenance projects and treatments are identified by Pavement Management staff at the time of design. In addition, federal funding requires that any funded project include necessary ADA improvements within the right-of-way.

The following estimated five-year maintenance need is based on ACHD’s Pavement Management Engineer’s evaluation of the StreetSaver Model’s Pavement Condition Index (PCI) data. This data is updated annually for Ada County arterials, collectors and residential streets. Funding also includes House Bill 312 maintenance funding.

Maintenance Program Name FY2020 FY2021 FY2022 FY2023 FY2024
Operational Maintenance (ACHD Forces) $9,530,000 $9,626,000 $9,723,000 $9,821,000 $9,920,000
Federal Aid Capital Maintenance $10,414,500 $8,199,000 $8,857,000 $8,659,000 $8,346,000
Local Capital Maintenance $7,343,000 $9,165,000 $9,013,000 $9,288,000 $9,830,000
Total $27,287,500 $26,990,000 $27,593,000 $27,768,000 $28,096,000

Bicycle and Pedestrian Improvements

Arterial roadways, with their higher traffic volumes require added consideration to safely accommodate bikes and pedestrians. These projects will install as appropriate, low-stress bike route alternatives, enhanced pedestrian crossings on arterial roadways, and fill sidewalk gaps. Enhanced crossings include Accessible Pedestrian Signals (APS), Pedestrian Hybrid Beacon (PHB) and Rectangular Rapid Flashing Beacon (RRFB).

Project Name Project Description Estimated Project Cost Local Match Possible Funding Sources
Vista Ave and Nez Perce St Install a PHB $259,000 $19,000 Transportation Alternatives (TA)
Hays St and 10th St and 11th St Install a RRFB $321,000 $24,000 TA
Overland Rd and Phillippi St Install a PHB $304,000 $23,000 TA
11th St Maintenance and Bikeway, State/Heron Complete roadway maintenance on 11th St from Fort to Heron and implement the 11th St Bikeway Concept $1,043,000 77,000 TA
Cassia St Bikeway and Pedestrian Improvements Improve Cassia St as a bikeway from Franklin to Kootenai. Includes pavement rehab, sidewalk, pedestrian bridge and enhanced pedestrian crossings $3,186,000 $234,000 TA
Kootenai St Traffic Calming, Orchard/Vista Implement components of the Kootenai St Traffic Calming Concept Study $1,477,000 $109,000 TA

Additional Maintenance and Safety Projects

The following is a list of additional maintenance and safety projects that staff will seek outside funding for:

Project Name Project Description Estimated Project Cost Local Match Possible Funding Sources
Fairview Ave Bridges #2196 & #2197 Reconstruct the existing deficient bridges over the Boise River $8.4 Million $617,000 to $3.4 Million BUILD, Federal Bridge Program and FASTLANE Grant
Replace Bridges That Create Flood Hazards Reconstruct obsolete bridge with design that eliminates 100-year flooding hazard created by existing bridge $500,000 to $2.0 Million $125,000 to $500,000 FEMA, Building Resilient Infrastructure and Communities (BRIC)
Replace Non-compliant Curb Ramps at Joint ACHD-ITD Intersections Bring non-compliant curb cuts up to ADA standards where ACHD sidewalks intersect ITD routes $60,000 $0 Idaho Americans with Disabilities Act Curb Ramp Program
Mini Roundabout Pilot Project To improve safety, convert the Rose Hill St/Owyhee St intersection; currently stop controlled for Owyhee St only, to a mini roundabout $300,000 $22,000 Local Highway Safety Improvement Program (LHSIP)
Orchard St and Clark St To improve safety, widen segment of Orchard to five lanes to accommodate left turn lane on Orchard St for vehicles turning onto Clark St $500,000 $37,000 LHSIP
Bike Lane Gap - Americana and 15th Street To improve safety, at intersection of 15th Street, widen Americana Boulevard roadway to the north to accommodate for consistent 5’ bike lanes $231,000 $17,000 LHSIP
Five Mile Rd, Overland Rd / Franklin Rd Working with ITD, reconstruct the existing bridge over Interstate 84 and widen adjacent legs of Five Mile Rd to five lanes $15,000,000 $1,100,000, less ITD’s portion BUILD Grant, Strategic Initiatives
Joint NEPA Study Conduct a NEPA study for a future joint bridge or road improvement project in coordination with an ACHD partner $250,000 $10,000 or half of match BUILD Grant
ACHD Enhanced Maintenance Project Apply for State funding to offset required roadway maintenance project that includes significant Complete Streets elements as part of ACHD planned projects Two grants up to $1,000,000 each No required match Local Strategic Initiatives Grant

Proactively Addressing Environmental Regulations

In response to existing and anticipated air quality and stormwater requirements, staff will seek grant funding that enables the District to implement innovative projects and training that prepares the District for broader regulatory requirements. Projects and training would focus on implementing stormwater projects that respond to lower Boise River Total Maximum Daily Load (TMDL) and NPDES permit requirements. In addition, staff will look for opportunities to improve ACHD operations with proven green technologies.

The following is a list of additional Primary Focus projects that staff will seek outside funding:

Project Name Project Description Estimated Project Cost Local Match Possible Funding Sources
GSI Technical Assistance Grant Technical assistance to develop a GSI Maintenance and Operations plan for the operation and maintenance of ACHD’s green infrastructure $50,000 As required EPA’s Technical Assistance Services for Communities program
GSI Infrastructure Supportive Curriculum To increase the number of qualified contractors with qualified staff, jointly develop with College of Western Idaho (CWI) a certified horticulture curriculum focused on the maintenance of stormwater facilities. $50,000 Min. $4,000 EPA Urban Waters Small Grant
GSI Infrastructure Projects Fund permeable paver retrofit of alleys in downtown Boise with cost-share from city $125,000 As required with City cost-share Federal source
GSI Infrastructure Projects Fund permeable paver retrofit of alleys adjacent to Meridian Community Center with cost-share from city $50,000 As required with City cost-share Federal source
GSI Infrastructure Projects Fund retrofit of stormwater system in Main/Fairview corridor with cost-share from city. Projects may include permeable alley, bioretention planters and tree planter $150,000 As required with City cost-share Transportation Alternatives and other Federal source
GSI and Air Quality Mitigation Demonstration Project Plant trees in identified locations to reduce stormwater impacts and improve regional air quality. $250,000 As required Idaho Department of Lands
Supporting Idaho Forrest Action Plan Pilot project to investigate processing and use of organic materials collected by ACHD street sweeping operations thereby eliminating this as a waste product. Funds will purchase necessary equipment $100,000 $10,000 Idaho Department of Lands
Replace or Upgrade Old Diesel Engines Replace existing construction equipment’s diesel motor with new clean diesel motor. $10,000 to $50,000 As required EPA and STP-TMA

Enhancement Projects

The following is a list of potential enhancement projects that staff will seek outside funding:

Project Name Project Description Estimated Project Cost Local Match Possible Funding Sources
Orchard St, Gowen Rd / I-84 On-Ramp Realign and widen to five lanes Orchard St from Gowen Rd to I-84. $5.4 million $1.0 million to 2.2 million BUILD and FASTLANE grants
ACHD-ITD Joint Intersections Partner with ITD to improve the ACHD portion of intersections with State Highway projects $500,000 to $10.0 million $19,000 to $2.0 million BUILD, STP-TMA and FASTLANE grants
Maintaining Power in an Emergency Purchase necessary stand-by power systems for both Adams Street and Cloverdale Road facilities $235,000 $59,000 Homeland Security Grant (HSGP), State Homeland Security (SHSP), Urban Areas Security Initiative (UASIP) and Emergency Management Performance Grants (EMPG)
Sidewalk Gaps Fill sidewalk gaps in existing ACHD system $150,000 $11,000 TAP
Implement Regional Low-Stress Bike Routes Seek funding to implement Bike Master Plan projects $25,000 to $500,000 $0 to $37,000 TAP
New Bike and Pedestrian Facility Evaluation Conduct study to evaluate the effectiveness of bike and pedestrian plans to integrate new facilities into the existing system $25,000 As required COMPASS Planning Grant
Wireless CCTV and Signal Interconnect Install wireless radio links to 20 intersections to interconnect signals and install remote CCTV camera link $150,000 $11,000 FHWA Program
Arterial Dynamic Message Signs Install four (4) arterial Dynamic Message Signs on major arterials to freeway interchanges $300,000 $22,000 FHWA Program
Purchase 13-Passenger Vans and Minivans For Commuteride fleet, purchase thirteen-seat vans and minivans to replace vehicles according to vehicle replacement schedule Varies per year 7.34% to 20% match FTA 5307Urbanized Area Formula, FTA 5339 or STP-TMA
Park and Ride Site Development Develop and construct park and ride site within Ada County to support the Commuteride program. Illustrative project would be parking lot with 50 to 75 parking spaces, located at 2nd Street and North Ave. B, in Kuna $1,000,000 $74,000 to $200,000 FTAor STP-TMA

Bridges Program

Major Bridge Projects

Project Name: Floating Feather Rd Bridge #2028, 580' E/O Munger Rd

  • Project Description: Replace/widen bridge #2028 over Middleton Canal on Floating Feather Rd as part of ACHD's Bridge Maintenance Program. Includes a detached pathway on the south side between Wild Mustang and Meadow Lake.
  • Project Program: Bridges Program
  • Project Sub-Program: Major Bridges
  • City Location: Star
  • Design Year: 2022
  • Design Cost: $183000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $108000
  • Construction Year: 2024
  • Construction Cost: $1731000
  • Project Manager: David Rader

Project Name: Gowen Rd Bridge #2110, W/O I-84

  • Project Description: Replace bridge #2110 over the UPRR tracks as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Major Bridges
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $197000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $363000
  • Construction Year: 2023
  • Construction Cost: $6471000
  • Project Manager: Brian McCarthy

Project Name: Pierce Park Ln Bridge #2029, at Hill Rd

  • Project Description: Replace bridge #2029 over the Farmers Union Canal on Pierce Park Ln as part of ACHD's Bridge Maintenance Program. Includes reconstruction of the intersection to the 2016 CIP configuration.
  • Project Program: Bridges Program
  • Project Sub-Program: Major Bridges
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $335000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $147000
  • Construction Year: 2024
  • Construction Cost: $1793000
  • Project Manager: Brian McCarthy

Minor Bridge Projects

Project Name: 11th St Bridge #1493, 90' N/O Main St

  • Project Description: Replace bridge #1493 over the Boise City Canal on 11th St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2023
  • Design Cost: $117000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $380000
  • Project Manager: Ryan Cutler

Project Name: 16th St Bridge #1484, 150' N/O Washington St

  • Project Description: Replace bridge #1484 over the Boise City Canal on 16th St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2024
  • Design Cost: $38000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $408000
  • Project Manager: Dale Kuperus

Project Name: 24th St Road and Bridge Projects

  • Project Description: Replace bridges #1466 on Irene St, #1467 on 24th St, and #1468 on Bella St over the Boise City Canal as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $52000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $13000
  • Construction Year: 2022
  • Construction Cost: $1177000
  • Project Manager: David Rader

Project Name: 26th St Bridge #1321, 160' S/O Hill Rd

  • Project Description: Replace bridge #1321 over the Boise City Canal on 26th St as part of ACHD's Bridge Maintenance Program. Includes sidewalk connection on the west side to Hill Rd.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $59000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $8000
  • Construction Year: 2023
  • Construction Cost: $336000
  • Project Manager: David Rader

Project Name: 32nd St Bridge #1308, 50’ S/O Hill Rd

  • Project Description: Replace bridge #1308 over the Boise City Canal on 32nd St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $37000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $241000
  • Project Manager: Seth Jarsky

Project Name: 33rd St Bridge #1318, 20’ S/O Forsythia St

  • Project Description: Replace bridge #1318 over the Boise City Canal on 33rd St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $37000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $285000
  • Project Manager: Seth Jarsky

Project Name: 37th St Bridge #1441, 350' SW/O Adams St

  • Project Description: Replace bridge #1441 over Thurman Mill on 37th St as part of ACHD's Bridge Maintenance Program. In-house design.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Garden City
  • Design Year: 2023
  • Design Cost: $0
  • Right-of-Way Year: 2023-2024
  • Right-of-Way Cost: $8000
  • Construction Year: Future
  • Construction Cost: $247000
  • Project Manager: Chris Dayley

Project Name: 38th St Bridge #1440, 0.2 miles N/O Chinden Blvd

  • Project Description: Replace bridge #1440 over the Thurman Mill Canal on 38th St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Garden City
  • Design Year: 2019-2020
  • Design Cost: $29000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $1000
  • Construction Year: 2021
  • Construction Cost: $251000
  • Project Manager: Chris Dayley

Project Name: 41st St Bridge #1437, 600' N/O Chinden Blvd

  • Project Description: Replace bridge #1437 over the Thurman Mill Canal on 41st St as part of ACHD's Bridge Maintenance Program. In-house design.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Garden City
  • Design Year: 2018
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $4000
  • Construction Year: 2021
  • Construction Cost: $107000
  • Project Manager: Jason Tugby

Project Name: 44th St Bridge #1433, 0.1 miles N/O Chinden Blvd

  • Project Description: Replace bridge #1433 over the Thurman Mill Canal on 44th St as part of ACHD's Bridge Maintenance Program. In-house design.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Garden City
  • Design Year: 2019
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $1000
  • Construction Year: 2021
  • Construction Cost: $175000
  • Project Manager: Jason Tugby

Project Name: 45th St Bridge #1432, 500' N/O Chinden Blvd

  • Project Description: Replace bridge #1432 over the Thurman Mill Canal on 45th St as part of ACHD's Bridge Maintenance Program. In-house design.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Garden City
  • Design Year: 2019
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $1000
  • Construction Year: 2022
  • Construction Cost: $132000
  • Project Manager: Jason Tugby

Project Name: Black Cat Rd Bridge #1305, 0.21 miles N/O King Rd

  • Project Description: Replace bridge #1305 over the Benton Lateral on Black Cat Rd as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Ada County
  • Design Year: 2022
  • Design Cost: $120000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $495000
  • Project Manager: Dale Kuperus

Project Name: Bridge Preventative Maintenance (2020)

  • Project Description: Bridge deck overlay and sealing of specified bridges. Locations to be identified as part of ACHD’s Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $50000
  • Project Manager: Dale Kuperus

Project Name: Bridge Preventative Maintenance (2021)

  • Project Description: Bridge deck overlay and sealing of specified bridges. Locations to be identified as part of ACHD’s Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $100000
  • Project Manager: Dale Kuperus

Project Name: Bridge Preventative Maintenance (2022)

  • Project Description: Bridge deck overlay and sealing of specified bridges. Locations to be identified as part of ACHD’s Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $100000
  • Project Manager: Dale Kuperus

Project Name: Bridge Preventative Maintenance (2023)

  • Project Description: Bridge deck overlay and sealing of specified bridges. Locations to be identified as part of ACHD’s Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $100000
  • Project Manager: Dale Kuperus

Project Name: Bridge Preventative Maintenance (2024)

  • Project Description: Bridge deck overlay and sealing of specified bridges. Locations to be identified as part of ACHD’s Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $100000
  • Project Manager: Dale Kuperus

Project Name: Bryson Ave Bridge #1134, 750' N/O Fairview Ave

  • Project Description: Replace bridge #1134 over the South Slough on Bryson Ave as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $0
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $3000
  • Construction Year: 2022
  • Construction Cost: $242000
  • Project Manager: Joe Tate

Project Name: Carlsbad Way Bridge #1419, 500' N/O State St

  • Project Description: Replace bridge #1419 over the Boise Valley Canal on Carlsbad Way as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $28000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $267000
  • Project Manager: Dale Kuperus

Project Name: Fiddler Dr Bridge #1510, 130' W/O Arlen Dr

  • Project Description: Replace bridge #1510 over the Zinger Lateral on Fiddler Dr as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $30000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: 2024
  • Construction Cost: $328000
  • Project Manager: Dale Kuperus

Project Name: Floating Feather Rd Bridge #1513, 0.1 miles E/O Palmer Ln

  • Project Description: Replace bridge #1513 over Foothill Ditch on Floating Feather Rd as part of ACHD's Bridge Maintenance Program. Project to be built in coordination with Palmer Ln Bridge #1009. In-house design.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Eagle
  • Design Year: 2021
  • Design Cost: $0
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $16000
  • Construction Year: 2023
  • Construction Cost: $110000
  • Project Manager: Brian McCarthy

Project Name: Gowen Rd Bridge #2173, 1.35 miles S/O Victory Rd

  • Project Description: Replace bridge #2173 over the New York Canal on Gowen Rd as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2018
  • Design Cost: $272000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $1000
  • Construction Year: 2020
  • Construction Cost: $1462000
  • Project Manager: Chris Dayley

Project Name: Hanley Pl Bridge #1056, 700' N/O Chaparral Rd

  • Project Description: Replace bridge #1056 over Willow Creek on Hanley Pl as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Ada County
  • Design Year: 2021
  • Design Cost: $105000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $17000
  • Construction Year: 2023
  • Construction Cost: $570000
  • Project Manager: Joe Tate

Project Name: Lena Ave Bridge #1509, 125' N/O Hickory Dr

  • Project Description: Replace bridge #1509 over the Zinger Lateral on Lena Ave as part of ACHD's Bridge Maintenance Program. In-house design.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $0
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $3000
  • Construction Year: 2023
  • Construction Cost: $274000
  • Project Manager: Brian McCarthy

Project Name: Locust Grove Rd Bridge #1207, 0.17 miles S/O Victory Rd

  • Project Description: Replace bridge #1207 over the Ten Mile Creek on Locust Grove Rd Rd as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Meridian
  • Design Year: 2023
  • Design Cost: $110000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $63000
  • Construction Year: Future
  • Construction Cost: $440000
  • Project Manager: Dale Kuperus

Project Name: Mallard Ave Bridge #1339, 650' W/O Parkcenter Blvd

  • Project Description: Replace bridge #1339 over Loggers Creek on Mallard Ave as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $99000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $22000
  • Construction Year: 2023
  • Construction Cost: $652000
  • Project Manager: Chris Dayley

Project Name: Munger Rd Bridge #1005 and #2001, 1/2 mile S/O New Hope Rd

  • Project Description: Replace bridge #1005 over the Dry Creek Canal and bridge #2001 over the Middleton Canal as part of ACHD's Bridge Maintenance Program. Road Trust Funds are available for this project.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Star
  • Design Year: 2023
  • Design Cost: $105000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $125000
  • Construction Year: Future
  • Construction Cost: $1040000
  • Project Manager: Ricardo Calderon

Project Name: Munger Rd Bridge #1462, 550' S/O New Hope Rd

  • Project Description: Replace bridge #1462 over Foothill Ditch on Munger Rd as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Star
  • Design Year: 2021
  • Design Cost: $45000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $29000
  • Construction Year: 2024
  • Construction Cost: $294000
  • Project Manager: Dale Kuperus

Project Name: Palmer Ln Bridge #1009, N/O Floating Feather Rd

  • Project Description: Replace bridge #1009 over Foothill Ditch on Palmer Ln as part of ACHD's Bridge Maintenance Program. In-house design. Project to be built in coordination with Floating Feather Rd Bridge #1513.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Star
  • Design Year: 2021
  • Design Cost: $0
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $3000
  • Construction Year: 2023
  • Construction Cost: $111000
  • Project Manager: Cody Homan

Project Name: Parkhill Dr Bridge #1383, 200' W/O 15th St

  • Project Description: Replace bridge #1383 over the Crane Creek on Parkhill Dr as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $50000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $3000
  • Construction Year: 2024
  • Construction Cost: $198000
  • Project Manager: Dale Kuperus

Project Name: Phillippi St Bridge #1366, 650' N/O Overland Rd

  • Project Description: Replace bridge #1366 over Farmers Lateral on Phillippi St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $49000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $7000
  • Construction Year: Future
  • Construction Cost: $361000
  • Project Manager: Dale Kuperus

Project Name: Shamrock Ave Bridge #1424, 0.1 miles N/O Fairview Ave

  • Project Description: Replace bridge #1424 over the South Slough on Shamrock Ave as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $25000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $37000
  • Construction Year: 2021
  • Construction Cost: $163000
  • Project Manager: Joe Tate

Project Name: Shoup Ave Bridge #1404, 0.25 miles W/O Maple Grove Rd

  • Project Description: Replace bridge #1404 over the Farmers Lateral on Shoup Ave as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $58000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $3000
  • Construction Year: 2023
  • Construction Cost: $245000
  • Project Manager: Cody Homan

Project Name: Star Rd Bridge #1093, 0.25 miles S/O McMillan Rd

  • Project Description: Replace bridge #1093 over Lawrence Kennedy Canal on Star Rd as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Ada County
  • Design Year: 2021
  • Design Cost: $50000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $3000
  • Construction Year: 2023
  • Construction Cost: $139000
  • Project Manager: Cody Homan

Project Name: Topaz Ave Bridge #1220, 0.1 miles N/O Overland Rd

  • Project Description: Replace bridge #1220 over the Five Mile Creek on Topaz Ave as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Meridian
  • Design Year: 2022
  • Design Cost: $22000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $4000
  • Construction Year: Future
  • Construction Cost: $555000
  • Project Manager: Dale Kuperus

Project Name: Wells St Bridge #1224, 0.2 miles S/O Magic View Dr

  • Project Description: Replace bridge #1224 over the Five Mile Creek on Wells St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Meridian
  • Design Year: 2024
  • Design Cost: $29000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $3000
  • Construction Year: Future
  • Construction Cost: $586000
  • Project Manager: Dale Kuperus

Project Name: Wildwood St Bridge #1425, 0.1 miles N/O Fairview Ave

  • Project Description: Replace bridge #1425 over the South Slough on Wildwood St as part of ACHD's Bridge Maintenance Program.
  • Project Program: Bridges Program
  • Project Sub-Program: Minor Bridges
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $61000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $61000
  • Construction Year: Future
  • Construction Cost: $307000
  • Project Manager: Dale Kuperus

Capital Investment Program

Cooperative Projects

Project Name: Corridor Preservation - Impact Fee Eligible (2020)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $1400000
  • Construction Year: 2020
  • Construction Cost: $1200000
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Impact Fee Eligible (2021)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $1400000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Impact Fee Eligible (2022)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $1500000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Impact Fee Eligible (2023)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $1500000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Impact Fee Eligible (2024)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $1500000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Non-Impact Fee Eligible (2020)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $590000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Non-Impact Fee Eligible (2021)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $300000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Non-Impact Fee Eligible (2022)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $200000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Non-Impact Fee Eligible (2023)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $200000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Corridor Preservation - Non-Impact Fee Eligible (2024)

  • Project Description: Purchase right-of-way and fund improvements in conjunction with development to protect and preserve transportation corridors as per the ACHD Master Street Map.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $200000
  • Construction Year: N/A
  • Construction Cost: $0
  • Project Manager: Christy Little

Project Name: Developers Cooperative Projects (2020)

  • Project Description: Fund ACHD's share of roadway projects done in conjunction with private developers.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $300000
  • Project Manager: Christy Little

Project Name: Developers Cooperative Projects (2021)

  • Project Description: Fund ACHD's share of roadway projects done in conjunction with private developers.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $300000
  • Project Manager: Christy Little

Project Name: Developers Cooperative Projects (2022)

  • Project Description: Fund ACHD's share of roadway projects done in conjunction with private developers.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $300000
  • Project Manager: Gary Inselman

Project Name: Developers Cooperative Projects (2023)

  • Project Description: Fund ACHD's share of roadway projects done in conjunction with private developers.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $300000
  • Project Manager: Gary Inselman

Project Name: Developers Cooperative Projects (2024)

  • Project Description: Fund ACHD's share of roadway projects done in conjunction with private developers.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $300000
  • Project Manager: Gary Inselman

Project Name: St. Luke's Master Plan Transportation Component Implementation (2021)

  • Project Description: Payment to St. Luke's for implementation of cooperative projects constructed as per the three party development agreement between ACHD, City of Boise, and St. Luke's approved on March 30, 2016.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $750000
  • Project Manager: Gary Inselman

Project Name: St. Luke's Master Plan Transportation Component Implementation (2022)

  • Project Description: Payment to St. Luke's for implementation of cooperative projects constructed as per the three party development agreement between ACHD, City of Boise, and St. Luke's approved on March 30, 2016.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $750000
  • Project Manager: Gary Inselman

Project Name: St. Luke's Master Plan Transportation Component Implementation (2023)

  • Project Description: Payment to St. Luke's for implementation of cooperative projects constructed as per the three party development agreement between ACHD, City of Boise, and St. Luke's approved on March 30, 2016.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $750000
  • Project Manager: Gary Inselman

Project Name: St. Luke's Master Plan Transportation Component Implementation (2024)

  • Project Description: Payment to St. Luke's for implementation of cooperative projects constructed as per the three party development agreement between ACHD, City of Boise, and St. Luke's approved on March 30, 2016.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $750000
  • Project Manager: Gary Inselman

Project Name: St. Luke's Master Plan Transportation Component Implementation (2025)

  • Project Description: Payment to St. Luke's for implementation of cooperative projects constructed as per the three party development agreement between ACHD, City of Boise, and St. Luke's approved on March 30, 2016.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Cooperative
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2025
  • Construction Cost: $750000
  • Project Manager: Gary Inselman

Intersection Projects

Project Name: Amity Rd and Maple Grove Rd

  • Project Description: Replace intersection with a multi-lane roundabout with a westbound right-turn bypass lane. Includes bridge #1243.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Ada County
  • Design Year: 2020
  • Design Cost: $365000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $435000
  • Construction Year: 2022-2023
  • Construction Cost: $3493000
  • Project Manager: Cody Homan

Project Name: Cole Rd and Franklin Rd

  • Project Description: Widen intersection to 7 lanes in all directions as per the 2016 CIP. Includes Cole Rd, I-84 / Franklin widening, realignment of the McMullen intersection, bridge #1259, and rail crossing improvements. Carryover from FY2019 construction project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Boise
  • Design Year: 2016-2017
  • Design Cost: $0
  • Right-of-Way Year: 2017-2018
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $3759000
  • Project Manager: Ryan Cutler

Project Name: Cole Rd and Victory Rd

  • Project Description: Widen intersection to 7 lanes in all directions with median U-turns as per the 2016 CIP. Includes Cole, McGlochlin/Victory widening, an enhanced crossing at Diamond, and bridge #1261.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Ada County, Boise
  • Design Year: 2018-2019
  • Design Cost: $750000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $1126000
  • Construction Year: 2020
  • Construction Cost: $8942000
  • Project Manager: Brian McCarthy

Project Name: Eagle Rd and State St

  • Project Description: Construct a quadrant intersection and widen Eagle Road between Plaza and State to 4 lanes with center median as per the Eagle Rd and State St Intersection Concept Study.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Eagle
  • Design Year: 2020
  • Design Cost: $555000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $878000
  • Construction Year: 2022
  • Construction Cost: $3650000
  • Project Manager: Ryan Cutler

Project Name: Fairview Ave and Locust Grove Rd

  • Project Description: Widen intersection to 8 lanes on Fairview Ave and 7 lanes on Locust Grove Rd, including concrete intersection, curb, gutter, sidewalk, and a Level 3 bike facility as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Meridian
  • Design Year: 2020-2021
  • Design Cost: $525000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $904000
  • Construction Year: 2022
  • Construction Cost: $3697000
  • Project Manager: Brian McCarthy

Project Name: Gowen Rd and Orchard St

  • Project Description: Reconstruct intersection in accordance with the Gowen Rd, Orchard St / I-84 Concept Study.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $145000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $271000
  • Construction Year: 2023
  • Construction Cost: $1380000
  • Project Manager: David Rader

Project Name: Lake Hazel Rd and Cloverdale Rd

  • Project Description: Widen intersection to 5 lanes on Lake Hazel Rd and 5 lanes on Cloverdale Rd as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Ada County
  • Design Year: 2022
  • Design Cost: $320000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $475000
  • Construction Year: 2024
  • Construction Cost: $3962000
  • Project Manager: Ricardo Calderon

Project Name: Lake Hazel Rd and Eagle Rd

  • Project Description: Widen and signalize intersection to 4/5 lanes on Eagle and 3/5 lanes on Lake Hazel as per the 2016 CIP. In-house design.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Meridian
  • Design Year: 2020
  • Design Cost: $70000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $549000
  • Construction Year: 2023
  • Construction Cost: $7759000
  • Project Manager: Joe Tate

Project Name: Lake Hazel Rd and Five Mile Rd

  • Project Description: Widen intersection to 6 lanes on Lake Hazel Rd and 5 lanes on Five Mile Rd as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Ada County
  • Design Year: 2018-2019
  • Design Cost: $333000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $950000
  • Construction Year: Future
  • Construction Cost: $2531000
  • Project Manager: Ryan Cutler

Project Name: Lake Hazel Rd and Maple Grove Rd

  • Project Description: Widen intersection to 6 lanes on Lake Hazel Rd and 4 lanes on Maple Grove Rd as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Ada County
  • Design Year: 2024
  • Design Cost: $300000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $648000
  • Construction Year: Future
  • Construction Cost: $4112000
  • Project Manager: Ryan Cutler

Project Name: Linder Rd and Deer Flat Rd

  • Project Description: Federal aid project to improve intersection of Linder Rd and Deer Flat Rd, including curb, gutter, sidewalk and bike facilities.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Boise
  • Design Year: 2017-2018
  • Design Cost: $663000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $514000
  • Construction Year: 2020
  • Construction Cost: $3880000
  • Project Manager: Joe Tate

Project Name: Linder Rd and Floating Feather Rd Roundabout

  • Project Description: Construct a multi-lane roundabout as per the 2016 CIP. To be built with the Linder Rd, State St (SH 44) / Floating Feather project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Eagle
  • Design Year: 2020-2021
  • Design Cost: $518000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $543000
  • Construction Year: 2024
  • Construction Cost: $3357000
  • Project Manager: Ricardo Calderon

Project Name: Overland Rd and Eagle Rd

  • Project Description: Widen intersection to 7 lanes on Eagle Rd and 9 lanes on Overland Rd as per the 2016 CIP. Project to be done in coordination with the Idaho Transportation Department.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Meridian
  • Design Year: Future
  • Design Cost: $585000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $1610000
  • Construction Year: Future
  • Construction Cost: $7145000
  • Project Manager: Ricardo Calderon

Project Name: State St and Glenwood St

  • Project Description: Widen intersection as per the State/Glenwood Intersection Concept Study, including median U-turns and improved bike and pedestrian crossings. Joint project with ITD.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Boise, Garden City
  • Design Year: Future
  • Design Cost: $300000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $160000
  • Construction Year: Future
  • Construction Cost: $5246000
  • Project Manager: Ricardo Calderon

Project Name: State St and Pierce Park Ln

  • Project Description: Widen intersection to 4 lanes (Pierce Park) and 7 lanes (State), including sidewalk/buffered bike lane (north) and pathway (south), median and bus pullouts as per the State St TTOP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Boise, Garden City
  • Design Year: 2018-2019
  • Design Cost: $637000
  • Right-of-Way Year: 2019-2020
  • Right-of-Way Cost: $2549000
  • Construction Year: 2021
  • Construction Cost: $7085000
  • Project Manager: Joe Tate

Project Name: Ten Mile Rd and Amity Rd

  • Project Description: Construct a multi-lane roundabout. Project includes Ten Mile Bridge #1182. In-house design.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Ada County
  • Design Year: 2018
  • Design Cost: $0
  • Right-of-Way Year: 2019-2020
  • Right-of-Way Cost: $244000
  • Construction Year: 2021
  • Construction Cost: $2453000
  • Project Manager: Brian McCarthy

Project Name: Ten Mile Rd and Columbia Rd

  • Project Description: Install a single-lane expandable roundabout as per the Ten Mile Corridor Intersection Analysis.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Kuna
  • Design Year: 2022
  • Design Cost: $500000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $103000
  • Construction Year: Future
  • Construction Cost: $1783000
  • Project Manager: David Rader

Project Name: Ten Mile Rd and Deer Flat Rd

  • Project Description: Install a single-lane expandable roundabout as per the Ten Mile Corridor Intersection Analysis.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Kuna
  • Design Year: 2024
  • Design Cost: $300000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $20000
  • Construction Year: Future
  • Construction Cost: $712000
  • Project Manager: David Rader

Project Name: Ten Mile Rd and Hubbard Rd

  • Project Description: Widen intersection or add roundabout as per the 2016 CIP. Traffic analysis should determine the ultimate lane configuration based on growth above projections in the area.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Kuna
  • Design Year: 2023
  • Design Cost: $300000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $30000
  • Construction Year: Future
  • Construction Cost: $1149000
  • Project Manager: Ricardo Calderon

Project Name: Ten Mile Rd and Lake Hazel Rd

  • Project Description: Widen intersection to 3/4 lanes on Ten Mile and 3/4 lanes on Lake Hazel as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Kuna
  • Design Year: 2021
  • Design Cost: $516000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $289000
  • Construction Year: 2023
  • Construction Cost: $3699000
  • Project Manager: Ricardo Calderon

Project Name: Ten Mile Rd and Victory Rd

  • Project Description: Construct a multi-lane roundabout. Includes bridge #1181.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Ada County
  • Design Year: 2019-2020
  • Design Cost: $173000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $216000
  • Construction Year: 2022-2023
  • Construction Cost: $2675000
  • Project Manager: Cody Homan

Project Name: US 20/26 (Chinden Blvd) and Curtis Rd

  • Project Description: Widen the intersection to add a dedicated southbound through/right turn lane as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Garden City
  • Design Year: 2018
  • Design Cost: $189000
  • Right-of-Way Year: 2019-2020
  • Right-of-Way Cost: $217000
  • Construction Year: 2022
  • Construction Cost: $1257000
  • Project Manager: Brian McCarthy

Project Name: US 20/26 (Chinden Blvd) and Locust Grove Rd

  • Project Description: Widen Locust Grove legs of intersection in conjunction with ITD project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Eagle, Meridian
  • Design Year: 2018-2019
  • Design Cost: $125000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $1700000
  • Project Manager: Brian McCarthy

Project Name: Victory Rd and Locust Grove Rd Roundabout

  • Project Description: Construct a multi-lane roundabout as per the 2016 CIP. Includes bridge #2116. In-house design.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Intersections
  • City Location: Meridian
  • Design Year: 2019
  • Design Cost: $61000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $620000
  • Construction Year: 2021
  • Construction Cost: $4336000
  • Project Manager: Ryan Cutler

Road Projects

Project Name: Cloverdale Rd, McMillan Rd / Chinden Blvd (US 20/26)

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk and bike lanes as per the 2016 CIP. Includes bridge #1129 and the intersection of Cloverdale and DeMeyer. Carryover from FY2019 construction project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: 2017
  • Design Cost: $0
  • Right-of-Way Year: 2018
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $1377000
  • Project Manager: Brian McCarthy

Project Name: Cloverdale Rd, Ustick Rd / McMillan Rd

  • Project Description: Widen Cloverdale Rd to 5 lanes with curb, gutter, sidewalk and bike lanes as per the Cloverdale Rd Concept Design and the 2016 CIP. Includes signalization of the Cloverdale and Edna intersection. Carryover from FY2019 construction project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: 2016
  • Design Cost: $0
  • Right-of-Way Year: 2017
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $1530000
  • Project Manager: Cody Homan

Project Name: Cloverdale Rd, Victory Rd / Overland Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk and raised bike lanes as per the 2016 CIP. Includes restriping of the Overland intersection.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: 2023
  • Design Cost: $1008000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $1075000
  • Construction Year: Future
  • Construction Cost: $6807000
  • Project Manager: Ryan Cutler

Project Name: Eagle Rd, Amity Rd / Victory Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk and a Level 3 bike facility as per the 2016 CIP. Includes an enhanced crossing at Rome and a roundabout at Eagle and Zaldia. In-house design.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2018
  • Design Cost: $16000
  • Right-of-Way Year: 2019-2020
  • Right-of-Way Cost: $525000
  • Construction Year: 2021
  • Construction Cost: $5014000
  • Project Manager: Ryan Cutler

Project Name: Eagle Rd, Lake Hazel Rd / Amity Rd

  • Project Description: Widen Eagle Rd to 5 lanes with curb, gutter, sidewalk and a Level 3 bike facility as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2021
  • Design Cost: $778000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $1314000
  • Construction Year: 2023
  • Construction Cost: $5129000
  • Project Manager: Brian McCarthy

Project Name: Five Mile Rd, Overland Rd / Franklin Rd

  • Project Description: Reconstruct/widen from 2-lanes to 5-lanes. Project costs do not include any work associated with the ITD Overpass.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: Future
  • Design Cost: $954000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $1131000
  • Construction Year: Future
  • Construction Cost: $10203000
  • Project Manager: Ryan Head

Project Name: Lake Hazel Rd, Cloverdale Rd / Five Mile Rd

  • Project Description: Widen Lake Hazel Rd to 5 lanes with curb, gutter, and 10' multi-use pathways as per the 2016 CIP and Bike Master Plan.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Ada County
  • Design Year: 2022
  • Design Cost: $896000
  • Right-of-Way Year: 2023-2024
  • Right-of-Way Cost: $765000
  • Construction Year: Future
  • Construction Cost: $5608000
  • Project Manager: Ryan Cutler

Project Name: Lake Hazel Rd, Eagle Rd / Cloverdale Rd

  • Project Description: Widen Lake Hazel Rd to 5 lanes with curb, gutter, and 10' multi-use pathways as per the 2016 CIP and Bike Master Plan.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Ada County
  • Design Year: 2022
  • Design Cost: $740000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $205000
  • Construction Year: 2024
  • Construction Cost: $7606000
  • Project Manager: Ricardo Calderon

Project Name: Lake Hazel Rd, Five Mile Rd / Maple Grove Rd

  • Project Description: Widen Lake Hazel Rd to 5 lanes with curb, gutter, and 10' multi-use pathways as per the 2016 CIP and Bike Master Plan.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Ada County
  • Design Year: 2023
  • Design Cost: $618000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $246000
  • Construction Year: Future
  • Construction Cost: $3785000
  • Project Manager: Ryan Cutler

Project Name: Lake Hazel Rd, Maple Grove Rd / Cole Rd

  • Project Description: Widen Lake Hazel Rd to 5 lanes with curb, gutter, and 10' multi-use pathways as per the 2016 CIP and Bike Master Plan.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Ada County
  • Design Year: 2024
  • Design Cost: $332000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $60000
  • Construction Year: Future
  • Construction Cost: $3665000
  • Project Manager: Brian McCarthy

Project Name: Linder Rd, Cayuse Creek Dr/ Chinden Blvd (US 20/26)

  • Project Description: Widen Linder Rd to 5 lanes with curb, gutter, sidewalk, and bike lanes as per the 2016 CIP. Includes bridge #1105 and an enhanced pedestrian crossing 0.25 miles S/O Chinden Blvd. Carryover from FY2019 construction project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2017
  • Design Cost: $0
  • Right-of-Way Year: 2018
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $121000
  • Project Manager: Cody Homan

Project Name: Linder Rd, Chinden Blvd (US 20/26) / SH 44 (State St) - South Phase

  • Project Description: Widen roadway to 5 lanes with detached multi-use pathways on Linder Rd, from Chinden Blvd to 1,000' N/O Artesian Rd. Right-of-way acquisition will be for the ultimate 7-lanes. The South Phase includes bridges #1078, #2033, and #2034.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Ada County
  • Design Year: 2024
  • Design Cost: $1879000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $1605000
  • Construction Year: Future
  • Construction Cost: $15305000
  • Project Manager: Ricardo Calderon

Project Name: Linder Rd, Franklin Rd / Pine Ave

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk, and bike lanes as per the 2016 CIP. Project includes bridge #1120. The UPRR crossing is being upgraded under a separate project concurrently.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2017-2018
  • Design Cost: $329000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $245000
  • Construction Year: 2020
  • Construction Cost: $2313000
  • Project Manager: David Rader

Project Name: Linder Rd, Overland Rd / Franklin Rd

  • Project Description: Widen Linder Rd to 5 lanes and construct a new 4-lane I-84 overpass, including curb, gutter, sidewalk, and bike lanes as per the 2016 CIP. Project would be a joint project between ACHD and ITD.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: Future
  • Design Cost: $1181000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $1924000
  • Construction Year: Future
  • Construction Cost: $13591000
  • Project Manager: Ryan Head

Project Name: Linder Rd, SH 44 (State St) / Floating Feather Rd

  • Project Description: Widen to 5 lanes, with curb, gutter, and multi-use pathways as per the 2016 CIP. Includes bridges #1021 and #1022.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Eagle
  • Design Year: 2021
  • Design Cost: $475000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $945000
  • Construction Year: 2024
  • Construction Cost: $5924000
  • Project Manager: Cody Homan

Project Name: Linder Rd, Ustick Rd / McMillan Rd

  • Project Description: Widen Linder Rd to 5 lanes with curb, gutter, sidewalk, and a Level 2 bike facility as per the 2016 CIP. Includes enhanced pedestrian crossings at Monument and Stone Valley. Carryover from FY2019 construction project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2017
  • Design Cost: $13000
  • Right-of-Way Year: 2018
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $1295000
  • Project Manager: Cody Homan

Project Name: Locust Grove Rd, Victory Rd / Overland Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk and a Level 2 bike facility as per the 2016 CIP. Includes enhanced crossing at Time Zone Dr and bridge #2087.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2019
  • Design Cost: $33000
  • Right-of-Way Year: 2020-2021
  • Right-of-Way Cost: $854000
  • Construction Year: 2022
  • Construction Cost: $7230000
  • Project Manager: Ryan Cutler

Project Name: Maple Grove Rd, Amity Rd / Victory Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk, and Level 2 bike facility as per the 2016 CIP. Includes bridges #1239.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Ada County
  • Design Year: 2022
  • Design Cost: $530000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2475000
  • Construction Year: 2024
  • Construction Cost: $7070000
  • Project Manager: Cody Homan

Project Name: Maple Grove Rd, Victory Rd / Overland Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk, and a Level 2 bike facility as per the 2016 CIP. Includes bridges #1237, #1238, and #1242 and enhanced crossings at Targee and Maple Grove Elementary.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: 2018
  • Design Cost: $558000
  • Right-of-Way Year: 2019-2020
  • Right-of-Way Cost: $1550000
  • Construction Year: 2021
  • Construction Cost: $6369000
  • Project Manager: Ryan Cutler

Project Name: Meridian Rd, Cherry Ln / Ustick Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk, and bike lanes as per the 2016 CIP. Includes bridges #2045 and #126X and enhanced crossings at James and Woodbury.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2016-2017
  • Design Cost: $327000
  • Right-of-Way Year: 2018-2019
  • Right-of-Way Cost: $2000
  • Construction Year: 2020
  • Construction Cost: $5287000
  • Project Manager: Brian McCarthy

Project Name: Orchard St Realignment, Gowen Rd / I-84 On-Ramp

  • Project Description: Realign/widen Orchard St to 5 lanes with curb, gutter, sidewalk, and a Level 3 bike facility as per the 2016 CIP.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $485000
  • Right-of-Way Year: 2021-2022
  • Right-of-Way Cost: $845000
  • Construction Year: 2023
  • Construction Cost: $4324000
  • Project Manager: David Rader

Project Name: State St, 36th St / 27th St

  • Project Description: Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk, and bike lanes as per the State St TTOP and the 2016 CIP. This project may include an access management component.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: Future
  • Design Cost: $370000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $720000
  • Construction Year: Future
  • Construction Cost: $4484000
  • Project Manager: Ricardo Calderon

Project Name: State St, Collister Dr / 36th St

  • Project Description: Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk, and bike lanes as per the State St TTOP and the 2016 CIP. This project may include an access management component.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise
  • Design Year: Future
  • Design Cost: $280000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $540000
  • Construction Year: Future
  • Construction Cost: $3493000
  • Project Manager: Ricardo Calderon

Project Name: State St, Glenwood St / Pierce Park Ln

  • Project Description: Widen State St to 7 Lanes between Glenwood and Hertford. Hertford to Pierce Park included with the State St and Pierce Park Ln intersection project.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise, Garden City
  • Design Year: Future
  • Design Cost: $210000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $460000
  • Construction Year: Future
  • Construction Cost: $2551000
  • Project Manager: Ricardo Calderon

Project Name: State St, Pierce Park Ln / Collister Dr

  • Project Description: Widen State St to 7 lanes with HOV/transit lanes, curb, gutter, sidewalk, and bike lanes as per the State St TTOP and the 2016 CIP. This project may include an access management component.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Boise, Garden City
  • Design Year: Future
  • Design Cost: $520000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $710000
  • Construction Year: Future
  • Construction Cost: $6452000
  • Project Manager: Ricardo Calderon

Project Name: Ten Mile Rd, McMillan Rd / Chinden Blvd (US 20/26)

  • Project Description: Widen Ten Mile Rd to 5 lanes with curb, gutter, sidewalk and bike lanes as per the 2016 CIP. Includes an enhanced pedestrian crossing at Malta. In-house design. To be built by development under a STARS agreement.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2018
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $198000
  • Construction Year: 2020
  • Construction Cost: $2019000
  • Project Manager: David Rader

Project Name: Ten Mile Rd, Ustick Rd / McMillan Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk and bike lanes as per the 2016 CIP. Includes bridges #1103 and #2204 and enhanced crossings at Tesino and the pedestrian path south of Vicenza.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Meridian
  • Design Year: 2018-2019
  • Design Cost: $512000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $36000
  • Construction Year: 2020-2021
  • Construction Cost: $7425000
  • Project Manager: David Rader

Project Name: Ten Mile Rd, Victory Rd / Overland Rd

  • Project Description: Widen to 5 lanes with curb, gutter, sidewalk and a Level 3 bike facility as per the 2016 CIP. In-house design.
  • Project Program: Capital Investment Program
  • Project Sub-Program: Roads
  • City Location: Ada County, Meridian
  • Design Year: 2019
  • Design Cost: $10000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $253000
  • Construction Year: 2022-2023
  • Construction Cost: $4272000
  • Project Manager: Cody Homan

Capital Maintenance Program

Federal Maintenance

Project Name: Federal Aid Capital Maintenance (2019) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise, Meridian
  • Design Year: 2017-2018
  • Design Cost: $492000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2019
  • Construction Cost: $603000
  • Project Manager: Cody Homan

Project Name: Federal Aid Capital Maintenance (2019) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise
  • Design Year: 2017-2018
  • Design Cost: $230000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2019
  • Construction Cost: $223000
  • Project Manager: Cody Homan

Project Name: Federal Aid Capital Maintenance (2019) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise
  • Design Year: 2017-2018
  • Design Cost: $83000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2019
  • Construction Cost: $189000
  • Project Manager: Cody Homan

Project Name: Federal Aid Capital Maintenance (2020) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Ada County, Boise, Eagle, Meridian
  • Design Year: 2018-2019
  • Design Cost: $308000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $5576000
  • Project Manager: Ryan Cutler

Project Name: Federal Aid Capital Maintenance (2020) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise
  • Design Year: 2018-2019
  • Design Cost: $193000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $2262000
  • Project Manager: Brian McCarthy

Project Name: Federal Aid Capital Maintenance (2020) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise
  • Design Year: 2018-2019
  • Design Cost: $58000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $300000
  • Project Manager: Brian McCarthy

Project Name: Federal Aid Capital Maintenance (2021) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $295000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $4948000
  • Project Manager: Brian McCarthy

Project Name: Federal Aid Capital Maintenance (2021) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $63000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $2120000
  • Project Manager: Joe Tate

Project Name: Federal Aid Capital Maintenance (2021) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Includes improvement to storm drain infrastructure.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $48000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $300000
  • Project Manager: David Rader

Project Name: Kuna Main St Revitalization, Avenue A / Avenue C - Maintenance

  • Project Description: Provide local match to support the Kuna Downtown Corridor Revitalization - Phase 2. Funds to be provided to Kuna to match a $700,000 Federal grant to cover roadway maintenance to be completed with the project.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: Kuna
  • Design Year: 2019
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $700000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2022) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2020
  • Design Cost: $543000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $5427000
  • Project Manager: Brian McCarthy

Project Name: Pavement Preservation & ADA (2022) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2020
  • Design Cost: $233000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $2326000
  • Project Manager: Ryan Cutler

Project Name: Pavement Preservation & ADA (2022) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Eligible for federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2020
  • Design Cost: $60000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $300000
  • Project Manager: Brian McCarthy

Project Name: Pavement Preservation & ADA (2023) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2021
  • Design Cost: $529000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $5291000
  • Project Manager: Seth Jarsky

Project Name: Pavement Preservation & ADA (2023) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2021
  • Design Cost: $222000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $2268000
  • Project Manager: Chris Dayley

Project Name: Pavement Preservation & ADA (2023) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Eligible for federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2021
  • Design Cost: $80000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $300000
  • Project Manager: Seth Jarsky

Project Name: Pavement Preservation & ADA (2024) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2022
  • Design Cost: $507000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $5072000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2024) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2022
  • Design Cost: $217000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $2174000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2024) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Eligible for federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2022
  • Design Cost: $80000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $300000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2025) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2023
  • Design Cost: $504000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2025
  • Construction Cost: $5043000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2025) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2023
  • Design Cost: $216000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2025
  • Construction Cost: $2161000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2025) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Eligible for federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2023
  • Design Cost: $80000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2025
  • Construction Cost: $300000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2026) - Phase 1

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2024
  • Design Cost: $504000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2026
  • Construction Cost: $5043000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2026) - Phase 2

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Project supplemented with federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2024
  • Design Cost: $216000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2026
  • Construction Cost: $2161000
  • Project Manager: Ricardo Calderon

Project Name: Pavement Preservation & ADA (2026) - Phase 3

  • Project Description: Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial and collector road segments. Projects selected as part of ACHD's Pavement Management Program. Eligible for federal-aid. Location TBD.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Federal
  • City Location: To Be Determined
  • Design Year: 2024
  • Design Cost: $80000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2026
  • Construction Cost: $300000
  • Project Manager: Ricardo Calderon

Local Maintenance Projects

Project Name: 11th St Maintenance and Bikeway, State St / Heron St

  • Project Description: Complete roadway maintenance on 11th St, from Fort St to Heron St and implement the 11th St Bikeway.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: 2020-2021
  • Design Cost: $153000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $2000
  • Construction Year: 2022
  • Construction Cost: $895000
  • Project Manager: David Rader

Project Name: Arterial & Collector Capital Maintenance (2020) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on identified arterial and collector roads as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Kuna, Meridian
  • Design Year: 2019
  • Design Cost: $42000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $1630000
  • Project Manager: Joe Tate

Project Name: Arterial & Collector Capital Maintenance (2021) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on identified arterial and collector roads as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2020
  • Design Cost: $50000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $1000000
  • Project Manager: Brian McCarthy

Project Name: Arterial & Collector Capital Maintenance (2022) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on identified arterial and collector roads as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2021
  • Design Cost: $50000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $1138000
  • Project Manager: Chris Dayley

Project Name: Arterial & Collector Capital Maintenance (2023) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on identified arterial and collector roads as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2022
  • Design Cost: $197000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $1816000
  • Project Manager: Scott Forrey

Project Name: Arterial & Collector Capital Maintenance (2024) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on identified arterial and collector roads as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2023
  • Design Cost: $230000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $2083000
  • Project Manager: Scott Forrey

Project Name: Arterial & Collector Capital Maintenance (2025) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on identified arterial and collector roads as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2024
  • Design Cost: $110000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2025
  • Construction Cost: $1000000
  • Project Manager: Scott Forrey

Project Name: Bannock St Maintenance and Bikeway, Broadway Ave / Greenbelt

  • Project Description: Complete roadway maintenance on Bannock St, from the flume to Coston St and implement the Bannock St Bikeway (East Phase).
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $75000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: 2024
  • Construction Cost: $617000
  • Project Manager: Ricardo Calderon

Project Name: Cul-de-Sac (2020) - HB312 Project

  • Project Description: Rehabilitate cul-de-sacs in Maintenance Zone 2 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Boise, Kuna, Meridian
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $460000
  • Project Manager: Ryan Cutler

Project Name: Cul-de-Sac (2021) - HB312 Project

  • Project Description: Rehabilitate cul-de-sacs in Maintenance Zone 2 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Boise, Kuna, Meridian
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $230000
  • Project Manager: David Rader

Project Name: Cul-de-Sac (2022) - HB312 Project

  • Project Description: Rehabilitate cul-de-sacs in Maintenance Zone 3 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Boise, Kuna, Meridian
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $400000
  • Project Manager: Scott Forrey

Project Name: Cul-de-Sac (2023) - HB312 Project

  • Project Description: Rehabilitate cul-de-sacs in Maintenance Zone 4 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $400000
  • Project Manager: Scott Forrey

Project Name: Cul-de-Sac (2024) - HB312 Project

  • Project Description: Rehabilitate cul-de-sacs in Maintenance Zone 5 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Boise, Garden City
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $400000
  • Project Manager: Scott Forrey

Project Name: Downtown Boise Implementation (2019) - HB312 Project

  • Project Description: Rehabilitate select streets in downtown Boise as per the Downtown Boise Implementation Plan. Includes an accessible pedestrian signal at 16th St and Idaho St. Project funded through House Bill 312 funding. Carryover from FY2019 construction project.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: 2018
  • Design Cost: $289000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2019
  • Construction Cost: $133000
  • Project Manager: Cody Homan

Project Name: Downtown Boise Implementation (2020) - HB312 Project

  • Project Description: Perform road rehabilitation of select streets in downtown Boise as per the Downtown Boise Implementation Plan. Project funded through House Bill 312 funding. Includes enhanced pedestrian crossings at State and 12th and State and 14th.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $327000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $3087000
  • Project Manager: Cody Homan

Project Name: Main St and Idaho St, 16th St / Broadway Ave - HB312 Project

  • Project Description: Rehabilitate Main St and Idaho St between 16th St and Broadway Ave as part of the Downtown Boise Implementation Plan. Project funded through House Bill 312 funding. Carryover from FY2019 construction project.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: 2017-2019
  • Design Cost: $162000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2019
  • Construction Cost: $263000
  • Project Manager: Cody Homan

Project Name: Maintenance Crack Seal (2020) - HB312 Project

  • Project Description: Seal cracks in arterial and collector roadways in Preventative Maintenance Zone 3 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Boise, Kuna, Meridian
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $385000
  • Project Manager: Seth Jarsky

Project Name: Maintenance Crack Seal (2021) - HB312 Project

  • Project Description: Seal cracks in arterial and collector roadways in Preventative Maintenance Zone 4 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $325000
  • Project Manager: Chris Dayley

Project Name: Maintenance Crack Seal (2022) - HB312 Project

  • Project Description: Seal cracks in arterial and collector roadways in Preventative Maintenance Zone 5 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Boise, Garden City
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $325000
  • Project Manager: Scott Forrey

Project Name: Maintenance Crack Seal (2023) - HB312 Project

  • Project Description: Seal cracks in arterial and collector roadways in Preventative Maintenance Zone 6 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County, Boise, Eagle, Meridian, Star
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $325000
  • Project Manager: Scott Forrey

Project Name: Maintenance Crack Seal (2024) - HB312 Project

  • Project Description: Seal cracks in arterial and collector roadways in Preventative Maintenance Zone 1 as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise, Garden City
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $325000
  • Project Manager: Scott Forrey

Project Name: Microseal (2020) - HB312 Project

  • Project Description: Microseal roadways as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $410000
  • Project Manager: Seth Jarsky

Project Name: Microseal (2021) - HB312 Project

  • Project Description: Microseal roadways as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $300000
  • Project Manager: Brian McCarthy

Project Name: Microseal (2022) - HB312 Project

  • Project Description: Microseal roadways as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $400000
  • Project Manager: Scott Forrey

Project Name: Microseal (2023) - HB312 Project

  • Project Description: Microseal roadways as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $400000
  • Project Manager: Scott Forrey

Project Name: Microseal (2024) - HB312 Project

  • Project Description: Microseal roadways as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $400000
  • Project Manager: Scott Forrey

Project Name: Orchard Access Rd Maintenance - HB312 Project

  • Project Description: Rehabilitate Orchard Access Rd between the Railroad Crossing to 2.75 miles S/O I-84 as part of ACHD's Pavement Management Program. Project funded all or in part through Hough Bill 312 funding. Carryover from FY2019 construction project.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Ada County
  • Design Year: 2019
  • Design Cost: $15000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $108000
  • Project Manager: Seth Jarsky

Project Name: Residential Capital Maintenance (2019) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design. Carryover from FY2019 construction project.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: 2018
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $80000
  • Project Manager: Seth Jarsky

Project Name: Residential Capital Maintenance (2020) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $64000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020-2021
  • Construction Cost: $3095000
  • Project Manager: Cody Homan

Project Name: Residential Capital Maintenance (2021) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: Meridian
  • Design Year: 2019
  • Design Cost: $66000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $2400000
  • Project Manager: David Rader

Project Name: Residential Capital Maintenance (2022) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2020
  • Design Cost: $100000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $4868000
  • Project Manager: Ryan Cutler

Project Name: Residential Capital Maintenance (2023) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding. In-house design.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2021
  • Design Cost: $110000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $5520000
  • Project Manager: Scott Forrey

Project Name: Residential Capital Maintenance (2024) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2022
  • Design Cost: $597000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $5503000
  • Project Manager: Scott Forrey

Project Name: Residential Capital Maintenance (2025) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2023
  • Design Cost: $597000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2025
  • Construction Cost: $5503000
  • Project Manager: Scott Forrey

Project Name: Residential Capital Maintenance (2026) - HB312 Project

  • Project Description: Pavement rehabilitation and pedestrian ramps on residential streets identified as part of ACHD's Pavement Management Program. Project funded through House Bill 312 funding.
  • Project Program: Capital Maintenance Program
  • Project Sub-Program: Local
  • City Location: To Be Determined
  • Design Year: 2024
  • Design Cost: $597000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2026
  • Construction Cost: $5503000
  • Project Manager: Scott Forrey

Community Programs

Bikeway Projects

Project Name: Bikeway Signage (2022)

  • Project Description: Install wayfinding and bikeway signage on improved bikeways as per the Bike Master Plan. Corridors include: Cloverdale Rd (Overland / Franklin), Main St & Fairview Ave (Greenbelt / Grove St), Protest Hill Bikeway, and Orchard Hill Bikeway.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $65000
  • Project Manager: Edinson Bautista

Project Name: Columbia Village Bikeway, Hwy 21 / Boise Ave

  • Project Description: Improve select streets (Holcomb, Yamhill, Lake Forest, Grand Forest) in Columbia Village as a bikeway to include wayfinding, signage, crossings, and markings as per the Bike Master Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2022-2023
  • Design Cost: $50000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $3000
  • Construction Year: 2024
  • Construction Cost: $192000
  • Project Manager: Seth Jarsky

Project Name: Columbus St Bikeway, Victory Rd / Kootenai St

  • Project Description: Improve Columbus St as a bikeway to include wayfinding and bikeway signage and markings as per the Bike Master Plan and the Central Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $20000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $6000
  • Construction Year: 2023
  • Construction Cost: $103000
  • Project Manager: Ryan Cutler

Project Name: Garden St Bikeway, Albion St / Greenbelt

  • Project Description: Improve Garden St as a bikeway to include wayfinding and bikeway signage, enhanced crossing at Franklin Rd, and markings as per the Bike Master Plan and the Central Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2024
  • Design Cost: $25000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $162000
  • Project Manager: Ryan Head

Project Name: Hollandale-Targee Bikeway, Locust Grove Rd / Targee St

  • Project Description: Improve select streets between Overland and Victory, including Hollandale, K Bar T, and Targee, as a continuous bikeway as per the Southwest Boise Neighborhood Plan and the Bike Master Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise, Meridian
  • Design Year: 2022-2023
  • Design Cost: $55000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $380000
  • Project Manager: Ryan Head

Project Name: Linder-Meridian Bikeway, Pine Ave / Temple Dr

  • Project Description: Improve as a bikeway select streets between Linder Rd and Meridian Rd to include wayfinding, bikeway signage, enhanced crossings at Ustick and McMillan, and markings as per the Bike Master Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Meridian
  • Design Year: 2024
  • Design Cost: $55000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $380000
  • Project Manager: Ryan Head

Project Name: Nez Perce St Bikeway, Orchard St / Columbus St

  • Project Description: Improve Nez Perce St as a low-stress bikeway to include wayfinding and bikeway signage, enhanced crossings, and markings as per the Bike Master Plan and the Central Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $25000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: 2023
  • Construction Cost: $205000
  • Project Manager: Ryan Head

Project Name: Northwest Boise Bikeway, Horseshoe Bend Rd / 36th St

  • Project Description: Improve select streets in Northwest Boise as a bikeway to include wayfinding, signage, enhanced crossings, and markings as per the Bike Master Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $25000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $2000
  • Construction Year: 2023
  • Construction Cost: $132000
  • Project Manager: Ryan Head

Project Name: Pleasanton Ave Bikeway, Greenbelt / 23rd St

  • Project Description: Improve Pleasanton Ave as a bikeway to include wayfinding and bikeway signage and markings as per the Bike Master Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2022-2023
  • Design Cost: $41000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: 2024
  • Construction Cost: $107000
  • Project Manager: Ryan Head

Project Name: School Ave Bikeway, King Rd / Deer Flat Rd

  • Project Description: Improve School Ave as a bikeway to include wayfinding and bikeway signage and markings as per the Bike Master Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Kuna
  • Design Year: 2023-2024
  • Design Cost: $41000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $55000
  • Project Manager: Ryan Head

Project Name: Shoshone St Bikeway, Canal St / Capital Blvd

  • Project Description: Improve Shoshone St as a bikeway network to include wayfinding, bikeway signage, a mini roundabout, enhanced connections at Overland, and markings as per the Shoshone Bikeway Concept.
  • Project Program: Community Programs
  • Project Sub-Program: Bikeways
  • City Location: Boise
  • Design Year: 2018-2019
  • Design Cost: $34000
  • Right-of-Way Year: 2019-2020
  • Right-of-Way Cost: $32000
  • Construction Year: 2020-2021
  • Construction Cost: $446000
  • Project Manager: Seth Jarsky

Core Community Projects

Project Name: Allumbaugh St, Fairview Ave / Northview St

  • Project Description: Complete curb, gutter, and sidewalk on the west side of Allumbaugh St, between Fairview Ave and Northview St.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $135000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $272000
  • Construction Year: 2024
  • Construction Cost: $479000
  • Project Manager: Ricardo Calderon

Project Name: Avenue C, Main St / 04th St

  • Project Description: Install curb, gutter, sidewalk, and angled parking on both sides of Avenue C from Main St to 04th St as per the Kuna Downtown Corridor Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Kuna
  • Design Year: 2021
  • Design Cost: $10000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $4000
  • Construction Year: 2022
  • Construction Cost: $282000
  • Project Manager: Seth Jarsky

Project Name: Avenue D, Main St / 04th St

  • Project Description: Install curb, gutter, sidewalk, and angled parking on both sides of Avenue D from Main St to 04th St as per the Kuna Downtown Corridor Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Kuna
  • Design Year: 2023
  • Design Cost: $34000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $3000
  • Construction Year: 2024
  • Construction Cost: $153000
  • Project Manager: Ricardo Calderon

Project Name: Broadway Ave, West 08th St / West 04th St

  • Project Description: Construct sidewalk on the south side of Broadway, from West 07th to West 04th as per the Downtown Meridian Neighborhood Plan. Includes pedestrian railing on the back side of sidewalk where it crosses Nine Mile Creek.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Meridian
  • Design Year: 2024
  • Design Cost: $113000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $395000
  • Project Manager: Ricardo Calderon

Project Name: Clay St, 34th St / 32nd St; 32nd St, Chinden Blvd / Clay St

  • Project Description: Construct curb, gutter, sidewalk, swales, landscaped bulb outs, and illumination on Clay from 34th to 32nd and on 32nd from Chinden to Clay in partnership with Garden City and Garden City URA.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Garden City
  • Design Year: 2022
  • Design Cost: $161000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $119000
  • Construction Year: 2024
  • Construction Cost: $1097000
  • Project Manager: David Rader

Project Name: Coston St, Bannock St / Franklin St

  • Project Description: Complete sidewalk on the west side of Coston, from Bannock to Franklin as per the East End Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $51000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: 2024
  • Construction Cost: $173000
  • Project Manager: Ricardo Calderon

Project Name: East 03rd St, Franklin Rd / Carlton St

  • Project Description: Construct streetscape improvements, including curb, gutter, sidewalk, and improved UPRR crossing, from Franklin to Carlton as per the Downtown Meridian Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Meridian
  • Design Year: 2023
  • Design Cost: $340000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $292000
  • Construction Year: Future
  • Construction Cost: $1349000
  • Project Manager: Ricardo Calderon

Project Name: East 2 1/2 St, Carlton Ave / Fairview Ave

  • Project Description: Construct sidewalk on the east side of East 2 1/2, from Carlton to Fairview as per the Downtown Meridian Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Meridian
  • Design Year: 2024
  • Design Cost: $77000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $74000
  • Construction Year: Future
  • Construction Cost: $242000
  • Project Manager: Ricardo Calderon

Project Name: Eckert Rd and Arrow Junction Dr Pedestrian Crossing

  • Project Description: Install crosswalk, curb ramps and lighting to improve pedestrian connectivity and safety at the intersection of Eckert Rd and Arrow Junction Dr. In-house design.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $0
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $3000
  • Construction Year: 2021
  • Construction Cost: $66000
  • Project Manager: Cody Homan

Project Name: Floating Feather Rd, Brandon Rd / Hornback Ave

  • Project Description: Construct sidewalk on the north side of Floating Feather Rd from Brandon Rd to Hornback Ave.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Star
  • Design Year: 2021
  • Design Cost: $0
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $48000
  • Construction Year: 2023
  • Construction Cost: $230000
  • Project Manager: Brian McCarthy

Project Name: Holcomb Rd, Mimosa Way / Amity Rd

  • Project Description: Construct sidewalk on the east side of Holcomb Rd from Mendota to Amity. Includes bike lane and wayfinding signage from Amity to Mimosa and an enhanced crossing at Amity.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2016
  • Design Cost: $4000
  • Right-of-Way Year: 2017
  • Right-of-Way Cost: $6000
  • Construction Year: 2020-2021
  • Construction Cost: $139000
  • Project Manager: David Rader

Project Name: Horseshoe Bend Rd and Floating Feather Rd

  • Project Description: Improve intersection for pedestrians, including curb ramps and sidewalk connection to improve pedestrian access and safety.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Eagle
  • Design Year: 2022
  • Design Cost: $59000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $3000
  • Construction Year: 2024
  • Construction Cost: $137000
  • Project Manager: Joe Tate

Project Name: Horseshoe Bend Rd and Shadowview St Pedestrian Crossing

  • Project Description: Install curb ramps, a striped pedestrian crossing, and refuge island on Horseshoe Bend Rd on the north side of Shadowview St. In-house design.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Eagle
  • Design Year: 2020
  • Design Cost: $0
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $3000
  • Construction Year: 2021
  • Construction Cost: $82000
  • Project Manager: Joe Tate

Project Name: Horseshoe Bend Rd, State St / Hill Rd

  • Project Description: Construct a pathway on the east side of Horseshoe Bend Rd as per the NW Boise Neighborhood Plan. Includes precast bridge, pedestrian crossing (Utahna St), and bikeway signage.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise, Eagle
  • Design Year: 2021
  • Design Cost: $125000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $275000
  • Construction Year: 2023
  • Construction Cost: $658000
  • Project Manager: Joe Tate

Project Name: Liberty St Sidewalk and Bikeway, Douglas St / Denton St

  • Project Description: Complete sidewalk on the east side of Liberty St, between Douglas St and Denton St as per the Central Bench Neighborhood Plan. Install bikeway signage between Franklin Rd and Emerald St.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $35000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $3000
  • Construction Year: 2023
  • Construction Cost: $483000
  • Project Manager: Ricardo Calderon

Project Name: Locust Grove Rd and Palermo Dr Pedestrian Crossing

  • Project Description: Install an enhanced pedestrian crossing (pedestrian hybrid beacon) across Locust Grove Rd at Palermo Dr.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Meridian
  • Design Year: 2023
  • Design Cost: $71000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $3000
  • Construction Year: Future
  • Construction Cost: $334000
  • Project Manager: Ricardo Calderon

Project Name: Locust Grove Rd and Woodbridge Dr Pedestrian Crossing

  • Project Description: Install an enhanced pedestrian crossing (pedestrian hybrid beacon) across Locust Grove, between Woodbridge and Watertower.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Meridian
  • Design Year: 2023
  • Design Cost: $24000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $3000
  • Construction Year: 2024
  • Construction Cost: $160000
  • Project Manager: Ricardo Calderon

Project Name: Maple Grove Rd and Edna St Pedestrian Crossing

  • Project Description: Install an enhanced pedestrian crossing (pedestrian hybrid beacon) across Maple Grove Rd at Edna St as per the West Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $36000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $11000
  • Construction Year: 2024
  • Construction Cost: $184000
  • Project Manager: Joe Tate

Project Name: McMillan Rd, Westview Dr / Maple Grove Rd

  • Project Description: Complete sidewalk on the south side and a pathway on the north side from Westview to Maple Grove as per the West Bench Neighborhood Plan. Includes an enhanced crossing at Mitchell. In-house design.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2016
  • Design Cost: $2000
  • Right-of-Way Year: 2017
  • Right-of-Way Cost: $26000
  • Construction Year: 2021
  • Construction Cost: $765000
  • Project Manager: Seth Jarsky

Project Name: Overland Rd and Phillippi St Pedestrian Crossing

  • Project Description: Install an enhanced crossing (pedestrian hybrid beacon) across Overland Rd at Phillippi St as per the Central Bench Neighborhood Plan. In-house design.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $0
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $6000
  • Construction Year: 2021
  • Construction Cost: $265000
  • Project Manager: Joe Tate

Project Name: Overland Rd, Columbus St / Federal Way

  • Project Description: Complete curb, gutter and sidewalk on Overland, Columbus to Federal Way as per the Central Bench Neighborhood Plan. Carryover from FY2019 construction project.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2015-2016
  • Design Cost: $12000
  • Right-of-Way Year: 2016
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $94000
  • Project Manager: Ryan Cutler

Project Name: Phillippi St, Malad St / Targee St

  • Project Description: Complete curb, gutter and sidewalk from Malad to Targee as per the Central Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2016
  • Design Cost: $46000
  • Right-of-Way Year: 2017
  • Right-of-Way Cost: $14000
  • Construction Year: 2021
  • Construction Cost: $504000
  • Project Manager: Joe Tate

Project Name: Phillippi St, Targee St / Overland Rd

  • Project Description: Construct curb, gutter, and sidewalk on the east side of Phillippi from Targee to Overland as per the Central Bench Neighborhood Plan. Includes partial road rehabilitation. In-house design.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2017
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $15000
  • Construction Year: 2021
  • Construction Cost: $901000
  • Project Manager: David Rader

Project Name: Plummer Rd Bridge #2002 Pedestrian Facilities, 1700' N/O SH 44

  • Project Description: Complete sidewalk on the west side of Plummer Rd by extending the bridge structure on the west side.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Star
  • Design Year: 2023
  • Design Cost: $115000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $24000
  • Construction Year: Future
  • Construction Cost: $524000
  • Project Manager: Joe Tate

Project Name: Roosevelt St, Rose Hill St / Emerald St

  • Project Description: Construct sidewalk on the west side of Roosevelt from Rose Hill to Emerald as per the Central Bench Neighborhood Plan. Project includes roadway rehabilitation.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2016
  • Design Cost: $249000
  • Right-of-Way Year: 2017
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $1234000
  • Project Manager: Brian McCarthy

Project Name: US 20/26 (Chinden Blvd) and 43rd St Pedestrian Crossing

  • Project Description: Federal aid project to install an enhanced crossing on Chinden Blvd at 43rd St.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Garden City
  • Design Year: 2021
  • Design Cost: $55000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $1000
  • Construction Year: 2023
  • Construction Cost: $159000
  • Project Manager: Brian McCarthy

Project Name: Victory Rd and Standing Timber Ave Pedestrian Crossing

  • Project Description: Install an enhanced crossing and curb ramps on Victory Rd at Standing Timber Ave.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Meridian
  • Design Year: 2018
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $148000
  • Project Manager: Joe Tate

Project Name: Vista Ave and Nez Perce St Pedestrian Crossing

  • Project Description: Install an enhanced crossing on Vista at Nez Perce, including bike push buttons. Includes relocation of bus stops closer to Nez Perce from Spaulding in coordination with Valley Regional Transit.
  • Project Program: Community Programs
  • Project Sub-Program: Core Community Projects
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $50000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $6000
  • Construction Year: 2022
  • Construction Cost: $227000
  • Project Manager: Chris Dayley

Economic Development Projects

Project Name: 05th St and 06th St, Myrtle St / Fort St, Two-Way Conversion

  • Project Description: Complete a 1-way to 2-way conversion of 05th St and 06th St in downtown Boise.
  • Project Program: Community Programs
  • Project Sub-Program: Economic Development
  • City Location: Boise
  • Design Year: 2018-2019
  • Design Cost: $160000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: Future
  • Construction Cost: $3004000
  • Project Manager: Cody Homan

Project Name: 05th St and Fort St and Hays St

  • Project Description: Improve intersection for pedestrians, bicyclists, and motorists. Project concept will determine the scope of intersection improvements.
  • Project Program: Community Programs
  • Project Sub-Program: Economic Development
  • City Location: Boise
  • Design Year: Future
  • Design Cost: $175000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $0
  • Construction Year: Future
  • Construction Cost: $0
  • Project Manager: Ricardo Calderon

Project Name: Aikens St, Eagle Rd / 02nd St

  • Project Description: Extend Aikens St, east to 02nd St from its current terminus and complete the street section with curb, gutter, and sidewalk as per the Eagle Rd and State St Intersection Concept Study.
  • Project Program: Community Programs
  • Project Sub-Program: Economic Development
  • City Location: Eagle
  • Design Year: 2018-2019
  • Design Cost: $134000
  • Right-of-Way Year: 2019-2020
  • Right-of-Way Cost: $201000
  • Construction Year: 2022
  • Construction Cost: $1411000
  • Project Manager: Cody Homan

Project Name: Broadway Ave/Avenue B and Idaho St/Warm Springs Ave

  • Project Description: Modify intersection as per the Broadway Ave / Avenue B and Idaho St / Warm Springs Ave Concept Design. Donna Larsen Park Pathway and pedestrian crossings being completed under a separate project.
  • Project Program: Community Programs
  • Project Sub-Program: Economic Development
  • City Location: Boise
  • Design Year: Future
  • Design Cost: $381000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $801000
  • Construction Year: Future
  • Construction Cost: $2994000
  • Project Manager: Ricardo Calderon

Project Name: Pine Ave, Meridian Rd / Locust Grove Rd - Roadway

  • Project Description: Reconstruct roadway including intersection widening, curb, gutter, sidewalk and bike lanes in partnership with Meridian and the Meridian Development Corporation. Project includes Pine Bridge #1126. FY2020 funding will complete basin re-vegetation.
  • Project Program: Community Programs
  • Project Sub-Program: Economic Development
  • City Location: Meridian
  • Design Year: 2016
  • Design Cost: $390000
  • Right-of-Way Year: 2017
  • Right-of-Way Cost: $0
  • Construction Year: 2018-2020
  • Construction Cost: $3995000
  • Project Manager: Cody Homan

Safe Sidewalk Projects

Project Name: Safe Sidewalk Program (2020)

  • Project Description: Repair sidewalk, replace non-compliant ramps, and fill sidewalk gaps to priority locations identified in ACHD's Americans with Disability Act Transition Plan. Project includes the Castle Hills, Pierce Park Meadows, and Gary Ln Meadows #5 subdivisions .
  • Project Program: Community Programs
  • Project Sub-Program: Safe Sidewalks
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $1600000
  • Project Manager: Ryan Fisher

Project Name: Safe Sidewalk Program (2021)

  • Project Description: Repair sidewalk, replace non-compliant ramps, and fill sidewalk gaps to priority locations identified in ACHD's Americans with Disability Act Transition Plan. Project includes the area of Fairview Ave to Northview St, Allumbaugh St / Curtis Rd.
  • Project Program: Community Programs
  • Project Sub-Program: Safe Sidewalks
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $1600000
  • Project Manager: Ryan Fisher

Project Name: Safe Sidewalk Program (2022)

  • Project Description: Repair sidewalk, replace non-compliant ramps, and fill sidewalk gaps to priority locations identified in ACHD's Americans with Disability Act Transition Plan. Project includes the area of Edna St to McMillan Rd, Shamrock Ave / Five Mile Rd.
  • Project Program: Community Programs
  • Project Sub-Program: Safe Sidewalks
  • City Location: Boise
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $1600000
  • Project Manager: Ryan Fisher

Project Name: Safe Sidewalk Program (2023)

  • Project Description: Repair sidewalk, replace non-compliant ramps, and fill sidewalk gaps to priority locations identified in ACHD's Americans with Disability Act Transition Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Safe Sidewalks
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $1600000
  • Project Manager: Ryan Fisher

Project Name: Safe Sidewalk Program (2024)

  • Project Description: Repair sidewalk, replace non-compliant ramps, and fill sidewalk gaps to priority locations identified in ACHD's Americans with Disability Act Transition Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Safe Sidewalks
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $1600000
  • Project Manager: Ryan Fisher

Vehicle Registration Fee Projects

Project Name: 09th St and Washington St Pedestrian Crossing

  • Project Description: Install an enhanced crossing (rectangular rapid flashing beacon) on 09th St at Washington St as per the North Boise Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $32000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $3000
  • Construction Year: 2023
  • Construction Cost: $141000
  • Project Manager: Chris Dayley

Project Name: 13th St Traffic Calming (Phase 1), Fort St / Hill Rd

  • Project Description: Implement components of the 13th St Traffic Calming Concept Study, including bulbouts at select intersections and an enhanced pedestrian crossing (rectangular rapid flashing beacon) of 13th St at Resseguie St.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $80000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $408000
  • Project Manager: Seth Jarsky

Project Name: 28th St, Hazel St / Irene St

  • Project Description: Construct bulb-outs at corners of the 28th St intersections of Irene St, Bella St, and Hazel St to provide traffic calming.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $49000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2020-2021
  • Construction Cost: $352000
  • Project Manager: David Rader

Project Name: 38th St, Bush Ave / Sunset Ave

  • Project Description: Extend roadway and complete sidewalk on both sides of 38th St from Bush Ave to Sunset Ave. Due to roadway elevation differences, project will require reconstruction of portions of the roadway.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $49000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $6000
  • Construction Year: 2022
  • Construction Cost: $370000
  • Project Manager: Brett Hubinger

Project Name: Bogart Ln, SH 44 (State St) / Sloan St

  • Project Description: Install an asphalt path with raised curb on the east side of Bogart between Pocono and Caswell and curb, gutter, and sidewalk on the east side at Sloan as per the NW Boise Plan. Includes an enhanced pedestrian crossing at Bogart and Sloan.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019-2020
  • Design Cost: $8000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $19000
  • Construction Year: 2022
  • Construction Cost: $252000
  • Project Manager: Chris Dayley

Project Name: Bogus Basin Rd, Curling Dr / 550' N/O Curling Dr

  • Project Description: Install curb, gutter, and sidewalk on both sides of Bogus Basin in a 550' gap north of Curling Dr as per the North Boise Neighborhood Plan. In-house design. Carryover from FY2019 construction project.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2018
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $17000
  • Construction Year: 2019-2020
  • Construction Cost: $42000
  • Project Manager: Jason Tugby

Project Name: Boise Ave and Linden St Pedestrian Crossing

  • Project Description: Install an enhanced crossing (rectangular rapid flashing beacon) on Boise Ave at Linden St as per the Southeast Boise Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $36000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $3000
  • Construction Year: 2023
  • Construction Cost: $123000
  • Project Manager: David Rader

Project Name: Broadway Ave and Boise Ave

  • Project Description: Improve intersection for bikes and pedestrians as per the Southeast Boise Neighborhood Plan. Includes accessible pedestrian signal.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $36000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $301000
  • Project Manager: Chris Dayley

Project Name: Cassia St Bikeway and Pedestrian Improvements

  • Project Description: Improve Cassia St as a bikeway from Franklin to Kootenai and sidewalk from Franklin Park to Curtis and Latah to Shoshone. Includes pavement rehabilitation, mini roundabout at Shoshone, pedestrian bridge at Cassia Park, and enhance pedestrian crossings.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2018-2019
  • Design Cost: $203000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $50000
  • Construction Year: 2021
  • Construction Cost: $2933000
  • Project Manager: Brian McCarthy

Project Name: Cherry Ln and Meridian Library Pedestrian Crossing

  • Project Description: Install an enhanced crossing (pedestrian hybrid beacon) on Cherry Lane between West 8th and Linder. This will require relocation of the existing school zone beacon to the west.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Meridian
  • Design Year: 2019
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $1000
  • Construction Year: 2020
  • Construction Cost: $266000
  • Project Manager: Jason Tugby

Project Name: Christine St, Northview St / Ustick Rd

  • Project Description: Construct sidewalk on both sides of Christine, from Northview to Ustick as per the West Bench Neighborhood Plan. Includes roadway rehabilitation. In-house design.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2017
  • Design Cost: $0
  • Right-of-Way Year: 2018
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $1014000
  • Project Manager: Joe Tate

Project Name: Columbus St, Overland Rd / Kootenai St

  • Project Description: Construct curb, gutter and sidewalk on Columbus from Overland to Kootenai as per the Central Bench Neighborhood Plan. Carryover from FY2019 construction project.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2016
  • Design Cost: $190000
  • Right-of-Way Year: 2017
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $336000
  • Project Manager: Ryan Cutler

Project Name: Cory Ln, Mitchell St / Maple Grove Rd

  • Project Description: Complete sidewalk on the north side of Cory Ln from Maple Grove Rd to Mitchell St as per the West Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2024
  • Design Cost: $45000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $100000
  • Construction Year: Future
  • Construction Cost: $195000
  • Project Manager: Seth Jarsky

Project Name: Deer Flat Rd and School Ave Pedestrian Crossing

  • Project Description: Install an enhanced pedestrian crossing (pedestrian hybrid beacon) on Deer Flat Rd at School Ave.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Kuna
  • Design Year: 2019
  • Design Cost: $35000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $1000
  • Construction Year: 2020-2021
  • Construction Cost: $217000
  • Project Manager: Jason Tugby

Project Name: Desert Ave, Latigo Dr / Round Up St

  • Project Description: Construct sidewalk within existing right-of-way on the south side of Desert Ave, between Latigo Dr and Round Up St.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Ada County
  • Design Year: 2023
  • Design Cost: $24000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $3000
  • Construction Year: Future
  • Construction Cost: $208000
  • Project Manager: Ricardo Calderon

Project Name: Enhanced School Crossings - Meridian Middle School and Capital High School

  • Project Description: Install enhanced pedestrian crossings (rectangular rapid flashing beacons) on West 08th St in front of Meridian Middle School and on Milwaukee St next to Capital High School at the existing crosswalks.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise, Meridian
  • Design Year: 2020
  • Design Cost: $25000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $5000
  • Construction Year: 2021
  • Construction Cost: $148000
  • Project Manager: Joe Tate

Project Name: Five Mile Rd and La Grange St Pedestrian Crossing

  • Project Description: Install an enhanced crossing on Five Mile at La Grange. Install an asphalt pathway with extruded curb on the east side of Five Mile, south La Grange St and on the south side of La Grange.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Ada County
  • Design Year: 2021
  • Design Cost: $45000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $2000
  • Construction Year: 2023
  • Construction Cost: $402000
  • Project Manager: Ricardo Calderon

Project Name: Franklin St, McKinley St / Pierce St

  • Project Description: Construct sidewalks on the north side of Franklin St, between McKinley St and Pierce St.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $42000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $2000
  • Construction Year: 2022
  • Construction Cost: $374000
  • Project Manager: Jason Tugby

Project Name: Garden St, Bethel St / Emerald St

  • Project Description: Construct sidewalks on the both sides of Garden St, between Bethel St and Emerald St as per the Central Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2024
  • Design Cost: $242000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $31000
  • Construction Year: Future
  • Construction Cost: $939000
  • Project Manager: Ricardo Calderon

Project Name: Garden St, Franklin Rd / Bethel St

  • Project Description: Construct sidewalks on the both sides of Garden St, between Franklin Rd and Bethel St as per the Central Bench Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $78000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $220000
  • Construction Year: 2022
  • Construction Cost: $989000
  • Project Manager: Seth Jarsky

Project Name: Hays St at 11th St and 12th St Pedestrian Crossings

  • Project Description: Install enhanced crossings (rectangular rapid flashing beacon) and pedestrian ramps to cross Hays St at 11th St and 12th St as per the North Boise Neighborhood Plan. 11th St crossing to be coordinated with the 11th St Maintenance and Bikeway project.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $67000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $4000
  • Construction Year: 2022
  • Construction Cost: $275000
  • Project Manager: David Rader

Project Name: Hazel St, 28th St / 26th St

  • Project Description: Construct detached sidewalk on the south side of Hazel St, between 28th St and 26th St.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2018-2019
  • Design Cost: $6000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2020-2021
  • Construction Cost: $39000
  • Project Manager: David Rader

Project Name: Kootenai St Traffic Calming, Orchard St / Vista Ave

  • Project Description: Implement components of the Kootenai St Traffic Calming Concept Study. Project to be completed in phases.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $150000
  • Right-of-Way Year: 2022
  • Right-of-Way Cost: $10000
  • Construction Year: 2023-2024
  • Construction Cost: $1321000
  • Project Manager: David Rader

Project Name: Kootenai St, Vista Ave / Federal Way

  • Project Description: Construct curb, gutter, sidewalks and bike lanes on Kootenai St from Vista Ave to Federal Way as per the Central Bench Neighborhood Plan. Project includes removal of on-street parking. Carryover from FY2019 construction project.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2015-2016
  • Design Cost: $0
  • Right-of-Way Year: 2016
  • Right-of-Way Cost: $0
  • Construction Year: 2019-2020
  • Construction Cost: $106000
  • Project Manager: Ryan Cutler

Project Name: Kuna Middle School Zone, Ten Mile Ave and Boise St

  • Project Description: Install school zone beacons on Ten Mile and Boise near Kuna Middle School. Includes lighting at Ten Mile and Sego Prairie.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Kuna
  • Design Year: 2021
  • Design Cost: $26000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $2000
  • Construction Year: 2022
  • Construction Cost: $165000
  • Project Manager: Seth Jarsky

Project Name: Linda Vista Ln, Canterbury Dr / Ustick Rd

  • Project Description: Complete curb, gutter, and sidewalk on west side of Linda Vista Ln from Canterbury Dr to Ustick Rd. Priority project request from the Boise School District.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2023
  • Design Cost: $113000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $59000
  • Construction Year: Future
  • Construction Cost: $760000
  • Project Manager: Ricardo Calderon

Project Name: Linder Rd, Main St / Deer Flat Rd

  • Project Description: Complete curb, gutter, sidewalk and a Level 3 bike facility on Linder Rd from 4th St to Deer Flat Rd. Project will construct an enhanced crossing at Porter St.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Kuna
  • Design Year: 2022
  • Design Cost: $30000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $133000
  • Construction Year: 2024
  • Construction Cost: $1474000
  • Project Manager: Joe Tate

Project Name: McMillan Rd and Leather Way Pedestrian Crossing

  • Project Description: Install an enhanced crossing (pedestrian hybrid beacon) on McMillan Rd at Leather Way. In-house design. Construction by ACHD forces.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $48000
  • Project Manager: Seth Jarsky

Project Name: Milwaukee St, Marcum St / Ustick Rd

  • Project Description: Install curb, gutter, and sidewalk on the west side of Milwaukee St from Marcum St to Ustick Rd. Sidewalk would be placed between the canal and the roadway.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2023
  • Design Cost: $160000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $33000
  • Construction Year: Future
  • Construction Cost: $971000
  • Project Manager: Ricardo Calderon

Project Name: Pierce St, Washington St / Shenandoah Dr

  • Project Description: Complete sidewalks on Pierce St from Washington to Shenandoah to improve pedestrian safety for students walking to Roosevelt Elementary. Includes road rehabilitation.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $112000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $517000
  • Project Manager: Chris Dayley

Project Name: Pollard Ln, Floating Feather Rd / Star Middle School

  • Project Description: Construct a 7' asphalt path on the west side of Pollard, between Floating Feather and Star Middle School and on Floating Feather, west of Pollard. Project includes a pedestrian bridge over the canal.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Star
  • Design Year: 2023
  • Design Cost: $32000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $2000
  • Construction Year: 2024
  • Construction Cost: $194000
  • Project Manager: David Rader

Project Name: Stoddard Rd, Victory Rd / Overland Rd

  • Project Description: Reconstruct Stoddard, between Victory and Overland to 3-lanes, sidewalks and bike lanes or multi-use paths. Project includes bridge #2085 and an enhanced crossing at Victory and Stoddard.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Meridian
  • Design Year: 2023
  • Design Cost: $309000
  • Right-of-Way Year: 2024
  • Right-of-Way Cost: $143000
  • Construction Year: Future
  • Construction Cost: $1530000
  • Project Manager: Ricardo Calderon

Project Name: Ten Mile Rd and Crenshaw St Pedestrian Crossing

  • Project Description: Install an enhanced crossing (pedestrian hybrid beacon) on Ten Mile Rd at Crenshaw St. In-house design. Construction by ACHD forces.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Kuna
  • Design Year: 2019
  • Design Cost: $0
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $2000
  • Construction Year: 2020
  • Construction Cost: $67000
  • Project Manager: Seth Jarsky

Project Name: Ustick Rd and Milwaukee St School Zone

  • Project Description: Expand the existing school zone by installing new school zone flashers on all legs of the intersection to improve student safety. Construction by ACHD forces.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $8000
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $2000
  • Construction Year: 2020
  • Construction Cost: $29000
  • Project Manager: David Rader

Project Name: Valley St, Lake Hazel Rd / La Grange St

  • Project Description: Complete curb, gutter, sidewalk, parking and bike facility on the west side of Valley St from Lake Hazel Rd to La Grange St.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Ada County
  • Design Year: 2019
  • Design Cost: $41000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $1000
  • Construction Year: 2021
  • Construction Cost: $412000
  • Project Manager: Chris Dayley

Project Name: Warm Springs Ave and Straughan Ave Pedestrian Crossing

  • Project Description: Install an enhance pedestrian crossing (rectangular rapid flashing beacon) on Warm Springs Ave at Straughan Ave as per the East End Neighborhood Plan.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2024
  • Design Cost: $27000
  • Right-of-Way Year: Future
  • Right-of-Way Cost: $2000
  • Construction Year: Future
  • Construction Cost: $156000
  • Project Manager: Ricardo Calderon

Project Name: Warm Springs Ave, Glacier Dr / Glacier Dr

  • Project Description: Construct sidewalk on the north side of Warm Springs Ave from 320' northwest of Glacier Dr to the southeast corner of Riverland Terrace Subdivision. Priority request from the Boise School District.
  • Project Program: Community Programs
  • Project Sub-Program: Vehicle Registration Fee Projects
  • City Location: Boise
  • Design Year: 2019
  • Design Cost: $49000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $292000
  • Project Manager: Joe Tate

Environmental Program

Project Name: Green Stormwater Implementation (2019)

  • Project Description: Reconstruct two alleys in downtown Boise identified as part of ACHD's National Pollutant Discharge Elimination System (NPDES) permit compliance program. Alleys are located south of Bannock, 4th / 5th and east of 10th, Miller / Myrtle.
  • Project Program: Environmental Program
  • Project Sub-Program:
  • City Location: Boise
  • Design Year: 2018
  • Design Cost: $78000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $332000
  • Project Manager: David Rader

Project Name: Green Stormwater Implementation (2022)

  • Project Description: Implement identified green stormwater infrastructure projects at select locations to be identified as part of ACHD's National Pollutant Discharge Elimination System (NPDES) permit compliance program.
  • Project Program: Environmental Program
  • Project Sub-Program:
  • City Location: To Be Determined
  • Design Year: 2021
  • Design Cost: $50000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $450000
  • Project Manager: Joe Tate

Project Name: Green Stormwater Implementation (2023)

  • Project Description: Implement identified green stormwater infrastructure projects at select locations to be identified as part of ACHD's National Pollutant Discharge Elimination System (NPDES) permit compliance program.
  • Project Program: Environmental Program
  • Project Sub-Program:
  • City Location: To Be Determined
  • Design Year: 2022
  • Design Cost: $50000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $450000
  • Project Manager: Erica Anderson-Maguire

Project Name: Green Stormwater Implementation (2024)

  • Project Description: Implement identified green stormwater infrastructure projects at select locations to be identified as part of ACHD's National Pollutant Discharge Elimination System (NPDES) permit compliance program.
  • Project Program: Environmental Program
  • Project Sub-Program:
  • City Location: To Be Determined
  • Design Year: 2023
  • Design Cost: $50000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $450000
  • Project Manager: Erica Anderson-Maguire

Project Name: Green Stormwater Implementation (2025)

  • Project Description: Implement identified green stormwater infrastructure projects at select locations to be identified as part of ACHD's National Pollutant Discharge Elimination System (NPDES) permit compliance program.
  • Project Program: Environmental Program
  • Project Sub-Program:
  • City Location: To Be Determined
  • Design Year: 2024
  • Design Cost: $50000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2025
  • Construction Cost: $450000
  • Project Manager: Erica Anderson-Maguire

Project Name: Thurman Mill Bridge Projects Water Quality Mitigation

  • Project Description: Provide water quality and quantity mitigation for a series of bridge projects being reconstructed in or near the Thurman Mill drainage area.
  • Project Program: Environmental Program
  • Project Sub-Program:
  • City Location: Garden City
  • Design Year: 2020
  • Design Cost: $50000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $163000
  • Construction Year: 2022
  • Construction Cost: $52000
  • Project Manager: Seth Jarsky

Project Name: Whitewater Park Blvd Basin #1009

  • Project Description: Modify stormwater basin #1009 to improve drainage and water quality.
  • Project Program: Environmental Program
  • Project Sub-Program:
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $200000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: Future
  • Construction Cost: $0
  • Project Manager: Dyan Bevins

Miscellaneous Program

Project Name: ACHD Headquarters - Stormwater Shed

  • Project Description: Construct a shed to support ACHD's stormwater monitoring efforts and operations.
  • Project Program: Miscellaneous Program
  • Project Sub-Program:
  • City Location: Garden City
  • Design Year: 2019
  • Design Cost: $0
  • Right-of-Way Year: 2019
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $135000
  • Project Manager: Dale Kuperus

Traffic Safety and Operations Program

Operations and Maintenance Projects

Project Name: Arterial Dynamic Message Sign Installation

  • Project Description: Install arterial DMS signs on major commuter routes such a Chinden Blvd, State St and Fairview Ave to provide incident, construction and travel time information to drivers.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $320000
  • Project Manager: Shawn Martin

Project Name: Eagle Rd Traffic Signal Improvements, I-84 / SH 44

  • Project Description: Replace traffic signal controllers and upgrade vehicle detection systems to improve traffic flow along Eagle Rd, I-84 / SH 44.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: Boise, Eagle, Meridian
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $450000
  • Project Manager: Shawn Martin

Project Name: Fiber Optic Cable Network Update

  • Project Description: Replace existing ACHD fiber or add additional fiber in existing conduit to improve operation of the ACHD network.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $100000
  • Project Manager: Shawn Martin

Project Name: Traffic Signals New and Upgraded (2020)

  • Project Description: Rebuild and upgrade selected traffic signals, including poles and mast arms, as well as detection and electrical systems. Includes funding to be used for Flashing Yellow Arrow controller upgrades.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $1500000
  • Project Manager: Shawn Martin

Project Name: Traffic Signals New and Upgraded (2021)

  • Project Description: Rebuild and upgrade selected traffic signals, including poles and mast arms, as well as detection and electrical systems.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2021
  • Construction Cost: $300000
  • Project Manager: Shawn Martin

Project Name: Traffic Signals New and Upgraded (2022)

  • Project Description: Rebuild and upgrade selected traffic signals, including poles and mast arms, as well as detection and electrical systems.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $300000
  • Project Manager: Shawn Martin

Project Name: Traffic Signals New and Upgraded (2023)

  • Project Description: Rebuild and upgrade selected traffic signals, including poles and mast arms, as well as detection and electrical systems.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2023
  • Construction Cost: $300000
  • Project Manager: Shawn Martin

Project Name: Traffic Signals New and Upgraded (2024)

  • Project Description: Rebuild and upgrade selected traffic signals, including poles and mast arms, as well as detection and electrical systems.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Operations and Maintenance
  • City Location: To Be Determined
  • Design Year: N/A
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2024
  • Construction Cost: $300000
  • Project Manager: Shawn Martin

Safety and Accessibility Projects

Project Name: Benjamin Ln and BVRR Crossing Improvement

  • Project Description: Install crossing signal, including constant warning detection, at the Boise Valley Railroad crossing of Benjamin Ln in Boise. Project to be design by the Idaho Department of Transportation in coordination with ACHD.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $10000
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2022
  • Construction Cost: $310000
  • Project Manager: Ricardo Calderon

Project Name: Fairview Ave and Curtis Rd Accessible Pedestrian Signal

  • Project Description: Replace pedestrian poles with Accessible Pedestrian Signal-compatible push buttons and replace pedestrian ramps with ADA compliant ramps.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $37000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $2000
  • Construction Year: 2021
  • Construction Cost: $392000
  • Project Manager: Ricardo Calderon

Project Name: Fairview Ave and Milwaukee St Accessible Pedestrian Signal

  • Project Description: Replace pedestrian poles with Accessible Pedestrian Signals and replace pedestrian ramps with ADA compliant ramps. Includes radius flattening of the southwest corner to minimize existing curb damage.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $24000
  • Right-of-Way Year: 2020
  • Right-of-Way Cost: $2000
  • Construction Year: 2021
  • Construction Cost: $229000
  • Project Manager: Ricardo Calderon

Project Name: Fairview Ave and Orchard St

  • Project Description: Replace pedestrian poles with Accessible Pedestrian Signal-compatible push buttons and replace pedestrian ramps with directional ramps. Project will also reduce the radius of the southwest corner.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Boise
  • Design Year: 2021
  • Design Cost: $53000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $2000
  • Construction Year: 2022
  • Construction Cost: $521000
  • Project Manager: Ricardo Calderon

Project Name: Linder Rd and UPRR Crossing Improvements

  • Project Description: Add warning lights and crossing gates at the crossing of Linder Rd and the Union Pacific railroad in Meridian. Project to be design by the Idaho Transportation Department in coordination with ACHD.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Meridian
  • Design Year: 2018
  • Design Cost: $0
  • Right-of-Way Year: N/A
  • Right-of-Way Cost: $0
  • Construction Year: 2020
  • Construction Cost: $510000
  • Project Manager: David Rader

Project Name: Orchard St and Clark St

  • Project Description: Install a left turn lane at the intersection of Orchard St and Clark St to enhance intersection safety.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $103000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $367000
  • Construction Year: 2024
  • Construction Cost: $641000
  • Project Manager: Ricardo Calderon

Project Name: Orchard St and Franklin Rd Accessible Pedestrian Signal

  • Project Description: Install Accessible Pedestrian Signals at the Franklin Rd and Orchard St intersection to enhance accessibility in compliance with the Americans with Disabilities Act.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Boise
  • Design Year: 2020
  • Design Cost: $43000
  • Right-of-Way Year: 2021
  • Right-of-Way Cost: $14000
  • Construction Year: 2022
  • Construction Cost: $84000
  • Project Manager: Seth Jarsky

Project Name: Rose Hill St and Owyhee St Mini Roundabout

  • Project Description: Replace the current two-way stop controlled intersection with a mini-roundabout to enhance intersection safety.
  • Project Program: Traffic Safety and Operations Program
  • Project Sub-Program: Safety and Accessibility
  • City Location: Boise
  • Design Year: 2022
  • Design Cost: $85000
  • Right-of-Way Year: 2023
  • Right-of-Way Cost: $17000
  • Construction Year: Future
  • Construction Cost: $244000
  • Project Manager: Ricardo Calderon